midpage
Projects
Sign in to see your projects.
73 F.4th 570
8th Cir.
2023
Read the full case

Background

  • The Bureau of Reclamation approved the Central North Dakota Water Supply Project (Sept. 2018 FONSI) to provide Garrison Diversion a 40-year water service contract for 20 cfs from the McClusky Canal (fed by Lake Audubon/Lake Sakakawea).
  • Proposed facilities: canal intake, wet well, pump station, and ~6-mile pipeline tying into the Red River Valley Project; only 0.10 miles of pipeline on Bureau land.
  • The Bureau relied on a 2013 Northwest Area Project study and supplemental EIS for cumulative-depletions analysis and listed the state-sponsored Red River Valley Project as a reasonably foreseeable action (volume increased from 122 to 165 cfs).
  • The Bureau concluded negligible impacts to the Missouri River mainstem, no measurable effect on reservoir levels, and no inter-basin transfer risk because (1) contract limits use to in-basin purposes and (2) flow meters/control valves would prevent out-of-basin withdrawals.
  • Missouri sued under the APA alleging violations of the Water Supply Act and NEPA; the district court granted summary judgment for defendants; the Eighth Circuit affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Bureau violated the Water Supply Act by proceeding without Congress when project modifications could affect Missouri River reservoir purposes Missouri: project modifies reservoir operations and therefore needed Congressional approval under 43 U.S.C. § 390b(e) Bureau/Defendants: project is authorized under the Garrison Diversion Act and other project-specific authorizations, so no additional Congressional approval under the Water Supply Act was required Held: Bureau reliance on Garrison Diversion Act was not arbitrary or unlawful; Missouri failed to show Water Supply Act violation
Whether NEPA required an EIS (segmentation/connected-actions) Missouri: Bureau improperly segmented analysis by excluding the state-sponsored Red River Valley Project and should have prepared an EIS Bureau: Red River Valley Project is a state action to be completed without federal approval, so it need not be aggregated; EA and incorporated analyses suffice Held: Connected-actions doctrine does not force aggregation of federal and non-federal actions; FONSI and EA were adequate — no EIS required
Adequacy of the Environmental Assessment: cumulative effects and downstream impacts Missouri: EA inadequately analyzed cumulative effects, downstream depletions, and inter-basin transfer risks Bureau: EA incorporated prior comprehensive study (Northwest Area Project), updated reasonably foreseeable actions, and addressed depletions and controls; technical assessments support negligible impacts Held: EA’s cumulative-effects and downstream analyses were not arbitrary or capricious; court defers to agency technical expertise
Adequacy of alternatives analysis in EA Missouri: Bureau considered only no-action alternative and failed to analyze shorter contracts, smaller volumes, or other sources Bureau: Project small in scope, minimal environmental effect, and alternatives were not raised in the administrative record; range of alternatives appropriately limited Held: Failure to analyze additional alternatives was not arbitrary; objections to unraised alternatives were forfeited

Key Cases Cited

  • Sierra Club v. Kimbell, 623 F.3d 549 (8th Cir. 2010) (NEPA "hard look" and EIS principles)
  • Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary and capricious standard)
  • Cent. S.D. Co-op Grazing Dist. v. Sec'y of U.S. Dep't of Agric., 266 F.3d 889 (8th Cir. 2001) (deference on technical agency determinations)
  • Heartwood, Inc. v. U.S. Forest Serv., 380 F.3d 428 (8th Cir. 2004) (standards for EA showing an EIS unnecessary)
  • Big Bend Conservation All. v. Fed. Energy Regul. Comm'n, 896 F.3d 418 (D.C. Cir. 2018) (connected-actions doctrine limits)
  • Ark. Wildlife Fed'n v. U.S. Army Corps of Eng'rs, 431 F.3d 1096 (8th Cir. 2005) (EA cumulative impacts and tiering)
  • Del. Riverkeeper Network v. Fed. Energy Reg. Comm'n, 45 F.4th 104 (D.C. Cir. 2022) (limited review of agency decision not to prepare an EIS)
  • Dep't of Transp. v. Public Citizen, 541 U.S. 752 (2004) (preservation of administrative comments on alternatives)
Read the full case

Case Details

Case Name: State of Missouri v. U.S. Department of Interior
Court Name: Court of Appeals for the Eighth Circuit
Date Published: Jul 10, 2023
Citations: 73 F.4th 570; 21-3408
Docket Number: 21-3408
Court Abbreviation: 8th Cir.
Log In
    State of Missouri v. U.S. Department of Interior, 73 F.4th 570