History
  • No items yet
midpage
971 N.E.2d 133
Ind. Ct. App.
2012
Read the full case

Background

  • There was a State–Larson contract for an airport project; Continental Electric (CE) bid as a subcontractor through Larson.
  • There was no contract between the State and CE, and no privity between CE and the State.
  • Clarification No. 1 and the Project Manual defined Alternate No. 2 as the diesel generator itself, with wiring treated as base-bid work.
  • Disputes over whether wiring between the building and the generator pad was in Alternate No. 2 or the base bid led to a State contracting officer’s decision favoring Larson’s interpretation.
  • CE claimed breach of contract and quantum meruit against the State; the trial court awarded CE unjust enrichment damages.
  • The appellate court reversed, holding CE could not recover against the State because there was no contract and no unjust enrichment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether CE may recover from the State for breach of contract. CE had performance benefiting the State; privity implied. No contract between State and CE; no privity; no direct breach. Reversed; no contract or privity to support breach.
Whether CE has a quantum meruit claim against the State. CE conferred measurable benefit and was unjustly enriched. No measurable benefit to State; benefit was to Larson; improper against State. Reversed; no unjust enrichment against the State.
Whether the four-part test for unjust enrichment applies to subcontractor claims against the State. Four-part test supports CE’s recovery. Test not satisfied; wiring was base bid; no implied request or unjust retention. Rejected; four-part test not satisfied against the State.
What was the proper scope of Alternate No. 2 and its relation to base bid wiring. Alternate No. 2 included more wiring; CE relied on this. Project Manual and CSO clarifications show wiring was base bid; Alternate No. 2 limited to generator. CE failed to show Alternate No. 2 included wiring; interpretation favored State.
Did the State’s response to CE’s Governor appeal violate due process or consent to dispute resolution? Governor’s denial of CE’s appeal without direct contract violated due process. No contract with CE; only Larson had Governor appeal rights; no due process violation. Reversed; court held no direct contractual basis for CE against State; due process not violated.

Key Cases Cited

  • Ochoa v. Ford, 641 N.E.2d 1042 (Ind. Ct. App. 1994) (mutual assent required for contract formation; missing terms negate contract)
  • Roberts v. Alcoa, Inc., 811 N.E.2d 466 (Ind. Ct. App. 2004) (unjust enrichment requires a measurable benefit and unjust retention)
  • MPACT Constr. v. Superior Concrete Constructors, 802 N.E.2d 901 (Ind. 2004) (no recovery when no contract or intended beneficiaries)
  • State Dept. of Natural Res. v. CCI, 860 N.E.2d 651 (Ind. Ct. App. 2007) (unjust enrichment four-part test applied to owner–subcontractor disputes)
  • Inlow v. Inlow, 797 N.E.2d 810 (Ind. Ct. App. 2004) (elements of unjust enrichment and implied contract)
  • Encore Hotels of Columbus, LLC v. Preferred Fire Prot., 765 N.E.2d 658 (Ind. Ct. App. 2002) (standard of review for trial court findings on contract issues)
  • Albright v. Bogue, 736 N.E.2d 782 (Ind. Ct. App. 2000) (fact-finding and credibility limitations in reviewing judgments)
Read the full case

Case Details

Case Name: State of Indiana Military Dept., State Armory Board of the State of Indiana, and Governor Mitch E. Daniels, Jr. v. Continental Electric Co., Inc.
Court Name: Indiana Court of Appeals
Date Published: Jul 17, 2012
Citations: 971 N.E.2d 133; 2012 Ind. App. LEXIS 334; 2012 WL 2904183; 45A05-11009-PL-465
Docket Number: 45A05-11009-PL-465
Court Abbreviation: Ind. Ct. App.
Log In
    State of Indiana Military Dept., State Armory Board of the State of Indiana, and Governor Mitch E. Daniels, Jr. v. Continental Electric Co., Inc., 971 N.E.2d 133