History
  • No items yet
midpage
4 N.E.3d 696
Ind. Ct. App.
2014
Read the full case

Background

  • In 2006 Indiana (FSSA) signed a 10-year, $1.3 billion Master Services Agreement (MSA) with IBM to modernize statewide welfare eligibility, call centers, and related services; IBM was paid ≈$437 million before termination.
  • The MSA set Policy Objectives focusing on timely, accurate eligibility determinations, expanded access, legal compliance, fraud deterrence, and improved work participation; Performance Standards (Schedule 10) and liquidated-damage mechanisms were incorporated.
  • Rollout proceeded regionally; implementation problems (unanswered calls, delayed processing, data issues) arose early, worsened by the 2007–09 recession, large disaster relief workloads, and scope expansions (e.g., Healthy Indiana Plan). CMS found federal eligibility-processing deficiencies in 2009.
  • State demanded Corrective Action Plan (July 2009); parties agreed one, but the State adopted a hybrid model and terminated the MSA for cause in October 2009. Both parties sued; six-week bench trial followed.
  • Trial court found no material breach by IBM, awarded IBM $40M in subcontractor assignment fees, ~$9.51M for equipment, ~$2.57M Early Termination Close Out Payments, denied Deferred Fees, and awarded prejudgment interest (~$10.6M). Appellate court reversed material-breach holding, affirmed some awards, reversed others, and remanded for damages and certain fee calculations.

Issues

Issue State (Plaintiff) Argument IBM (Defendant) Argument Held
Was IBM’s failure a material breach of the MSA? IBM’s repeated failures (timeliness, Help Center, case processing), CMS warnings, and Schedule 10 misses went to the contract’s heart and justified termination for cause. IBM performed substantially, produced important benefits (fraud reduction, improved participation, systems/platforms), paid liquidated damages for KPI misses, and was curing problems. Court: IBM materially breached the MSA — failures on core Policy Objectives (timely, reliable services complying with federal law) went to the essence. Reversed trial court’s no-material-breach finding; remanded for State damages and offsets.
Are the $40M subcontractor assignment fees enforceable or an unenforceable penalty? State: fees are fixed-sum cancellation penalties contingent on termination; unenforceable liquidated damages/penalty. IBM: fees were bargained consideration for valuable rights (State’s ability to assume IBM’s subcontracts and associated benefits). Court: Fees are valid consideration (not liquidated damages) because contingent on State’s assumption of subcontracts and confer measurable benefit; award of $40M affirmed.
Are Deferred Fees / Early Termination Close Out Payments and Equipment payments payable after termination for cause? State: where termination is for cause Deferred Fees and ET Close Out Payments are excluded; cannot be recovered. Equipment likewise not payable if termination for cause. IBM: some Close Out payments and Deferred Fees are payable on termination generally; Equipment value is due because State kept IBM property per Disengagement Plan. Court: Deferred Fees and Early Termination Close Out Payments not payable where contract terminated for cause (affirming denial of Deferred Fees and reversing $2.57M award). But Equipment — State kept IBM equipment and must pay fair market value — $9.51M award affirmed.
Change Orders and prejudgment interest: entitlement to fees for Change Orders 119/133; is prejudgment interest recoverable from the State? State: Change Orders pre-dated MSA or were IBM’s responsibility; prejudgment interest barred by sovereign immunity and MSA language. IBM: executed Change Orders entitle it to negotiated fees (at least for 119,133); MSA permits recovery of interest and IBM preserved claim. Court: Trial court erred denying fees for COs 119 and 133 — remanded to calculate amounts; COs 71 and 102 lacked executed change orders so no recovery. Prejudgment interest award reversed — State did not waive sovereign immunity or clearly bind itself to pay prejudgment interest under the MSA/statutes cited.

Key Cases Cited

  • Citimortgage, Inc. v. Barabas, 975 N.E.2d 805 (Ind. 2012) (contract interpretation starts with plain language; ambiguity allows extrinsic evidence)
  • Collins v. McKinney, 871 N.E.2d 363 (Ind. Ct. App. 2007) (factors to assess whether a breach is material)
  • Ream v. Yankee Park Homeowner’s Ass’n, Inc., 915 N.E.2d 536 (Ind. Ct. App. 2009) (material-breach principles and damages consequences)
  • Steve Silveus Ins., Inc. v. Goshert, 873 N.E.2d 165 (Ind. Ct. App. 2007) (material breach goes to the heart of the contract)
  • Ind. Dep’t of Pub. Welfare v. Chair Lance Serv., Inc., 523 N.E.2d 1373 (Ind. 1988) (sovereign immunity bars prejudgment interest against the State unless waived by statute or contract)
Read the full case

Case Details

Case Name: State of Indiana, acting on behalf of the Indiana Family & Social Services Administration v. International Business Machines Corporation
Court Name: Indiana Court of Appeals
Date Published: Feb 13, 2014
Citations: 4 N.E.3d 696; 2014 Ind. App. LEXIS 54; 2014 WL 561658; 49A02-1211-PL-875
Docket Number: 49A02-1211-PL-875
Court Abbreviation: Ind. Ct. App.
Log In