History
  • No items yet
midpage
242 A.3d 1188
Md. Ct. Spec. App.
2020
Read the full case

Background

  • SHA pre-certified Faddis’s Downingtown plant and approved a sample panel in Sept. 2013; Brawner was the prime contractor on the I‑95 noise‑barrier project and subcontracted production of panels to Faddis (purchase order, Feb. 2013).
  • SHA inspectors later found production and quality problems (including use of unapproved aggregate and altered test data); SHA suspended purchases and notified Brawner in May 2014.
  • Faddis sent letters in June 2014 asking Brawner to forward claims to SHA; Brawner’s May 8, 2014 letter reserved rights but did not present a claim on Faddis’s behalf.
  • Faddis sued Brawner in federal court (July 2015) alleging Brawner refused to "pass through" Faddis’s claims to SHA; Brawner forwarded the federal complaint to SHA on Aug. 11, 2015 (which SHA treated as a notice of claim).
  • MSBCA granted SHA summary disposition: (1) Faddis, as a subcontractor with no direct procurement contract with SHA, lacked standing to file directly; (2) any pass‑through claim by Brawner on Faddis’s behalf was untimely (notice not filed within 30 days). The Circuit Court reversed; the Court of Special Appeals reversed the Circuit Court and remanded to affirm MSBCA.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Faddis is a "procurement contractor" with standing to file a direct contract claim against SHA Faddis: SHA’s pre‑certification and sample approval created an agreement/contract and made Faddis a procurement contractor eligible to sue directly SHA: A "procurement contract" requires a direct contract with the procurement agency; pre‑approval does not create such a contract Held: Pre‑approval/certification is not a procurement contract; Faddis lacked standing to file directly
Whether Brawner timely filed a pass‑through notice of claim on behalf of Faddis Brawner/Faddis: May 8 letter or other communications created factual disputes so timeliness requires a full hearing SHA: No written pass‑through notice was filed within 30 days of the claim’s accrual; August 2015 notice was too late Held: No timely pass‑through notice; statutory 30‑day requirement violated; claim dismissed as untimely
Interpretation of "procurement contract" and waiver of sovereign immunity Faddis: statutory definitions (procurement/procurement contract) encompass pre‑approval/eligibility arrangements SHA: Waiver of sovereign immunity is narrow; Legislature requires a written/direct contract with the agency to invoke contract remedies Held: Waiver construed narrowly; procurement contract requires direct contractual relationship with the State
Appropriateness of MSBCA summary disposition Faddis/Brawner: factual disputes exist (timeliness, whether May 8 constituted notice) and summary disposition improper SHA: Record documents are dispositive; no genuine issue of material fact Held: MSBCA correctly granted summary disposition; documents establish lack of standing and untimeliness

Key Cases Cited

  • Comptroller v. Science Applications, 405 Md. 185 (2008) (standard of appellate review of administrative agency decisions)
  • Motor Vehicle Admin. v. Pollard, 466 Md. 531 (2019) (confirms review standard for agency decisions)
  • Engineering Management v. State Highway Administration, 375 Md. 211 (2003) (timeliness of claims and evidentiary hearing context)
  • ARA Health v. Dept. of Public Safety, 344 Md. 85 (1996) (Legislature may waive sovereign immunity directly or by necessary implication)
  • Katz v. Washington Sub. San. Comm’n, 284 Md. 503 (1979) (background on Maryland sovereign immunity)
Read the full case

Case Details

Case Name: State Highway Admin v. Brawner Builders
Court Name: Court of Special Appeals of Maryland
Date Published: Dec 18, 2020
Citations: 242 A.3d 1188; 248 Md. App. 646; 1643/19
Docket Number: 1643/19
Court Abbreviation: Md. Ct. Spec. App.
Log In