History
  • No items yet
midpage
State Ex Rel. Dept. of Education v. Vantage Technologies
243 Or. App. 557
Or. Ct. App.
2011
Read the full case

Background

  • In March 2001, DOE contracted with Vantage to provide and administer TES A software for K‑12 testing, with base testing volume 540,292 and up to 1,000 concurrent users in Phase I and increasing in later phases.
  • The contract included a not‑to‑exceed liability initially of $3,179,600 for the first five years, later amended to higher totals, and Exhibit B set annual costs and deliverables for each phase.
  • Section 11.2 provided that if DOE delivered more than 110% (594,321) of the base volume in a contract year, DOE would negotiate in good faith to establish a new pricing structure.
  • Amendment A5 (May 29, 2004) removed the 500,000 (later stated as 540,292 base) test limit and increased Phase V costs; it also listed specific deliverables and included a broad equitable-adjustment release, while stating that other terms remained in force.
  • After 2004, testing volume exceeded 594,321, and the parties disputed whether Amendment A5 eliminated the obligation to negotiate a new pricing structure or merely expanded capacity.
  • The trial court held the contract ambiguously interpreted and submitted the issue to the jury; the jury awarded Vantage approximately $3.52 million, which DOE challenged on appeal.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did Amendment A5 eliminate the need to negotiate under 11.2 when tests exceeded 594,321? DOE: A5's removal of the limit and related terms eliminated 11.2's negotiation obligation. Vantage: Amendments addressed capacity only and did not extinguish 11.2's requirement to negotiate. Ambiguity; jury to decide.
Is the contract, including Amendment A5, ambiguous as to how pricing is adjusted for excess tests? DOE contends the amendment and integration clause render the pricing obligation unambiguous. Vantage contends the language is plausible to require negotiations or a new pricing structure. Ambiguity; jury to decide.
Did the integration clause and full‑integration provision affect the interpretation of Amendment A5 and 11.2? DOE argues the integration clause requires written amendments for any obligation beyond the original terms. Vantage contends amendment preserved 11.2 and did not require retroactive changes. Ambiguity; jury to decide.
Did the waiver/ Release clause in Amendment A5 bar claims for additional costs beyond those specified? DOE asserts the release provision bars additional equitable adjustments. Vantage argues the clause relates to capacity adjustments, not to the ongoing pricing obligation of 11.2. Ambiguity; jury to decide.

Key Cases Cited

  • Dalton v. Robert Jahn Corp., 209 Or.App. 120 (2006) (objective theory of contracts; focus on express terms)
  • Yogman v. Parrott, 325 Or. 358 (1997) (ambiguous contract risk; extrinsic evidence may be used)
  • Batzer Construction, Inc. v. Boyer, 204 Or.App. 309 (2006) (extrinsic evidence to determine contract ambiguity)
  • Evenson Masonry, Inc. v. Eldred, 273 Or. 770 (1975) (contract interpretation; binding if supported by record)
  • Harnisch v. College of Legal Arts, Inc., 243 Or.App. 16 (2011) (intent and ambiguity analysis in contract interpretation)
Read the full case

Case Details

Case Name: State Ex Rel. Dept. of Education v. Vantage Technologies
Court Name: Court of Appeals of Oregon
Date Published: Jun 22, 2011
Citation: 243 Or. App. 557
Docket Number: 07C12927; A141945
Court Abbreviation: Or. Ct. App.