History
  • No items yet
midpage
Stark Excavating v. Carter Construction Services
2012 IL App (4th) 110357
| Ill. App. Ct. | 2012
Read the full case

Background

  • Stark filed a third-amended complaint alleging breach of contract for winter protection work, other extras, and retainage, plus quantum meruit and unjust enrichment claims for winter protection costs.
  • The subcontract with Carter excluded winter protection of concrete or subgrade from the contract price, though winter-related costs were contemplated; Stark sought payment for winter protection as an extra.
  • Carter moved to dismiss and later moved for summary judgment; the trial court found winter protection was excluded and denied payment under Watson, granting summary judgment to Carter.
  • Stark’s December 2005 letters showed Stark intended to document costs outside the contract; Carter would not sign non‑preapproved work orders, but Stark proceeded.
  • The trial court granted summary judgment on the winter protection extra, and Stark sued on quasi-contractual theories; the court later dismissed counts II and III, then Stark amended, and the case was appealed.
  • The appellate court reversed and remanded, holding a triable issue of fact existed as to whether Stark could recover winter-protection costs under Watson-based analysis and that quasi-contractual claims could proceed, while affirming dismissal of the contract claim on count I was improper in light of factual questions.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Stark can recover for winter protection as an extra under Watson. Stark could prove the winter protection work was beyond the contract and ordered by Carter, with a written waiver not needed. Winter protection was expressly excluded from the contract and not approved as an extra. There are genuine issues of material fact; summary judgment was improper.
Whether Stark may recover for winter protection under quasi-contractual theories. Quasi-contractual recovery is available because winter protection was not covered by the contract. No recovery under quasi-contractual theories if contract covers the subject matter. Genuine issues of material fact exist; quasi-contractual claims should proceed.

Key Cases Cited

  • Watson Lumber Co. v. Guennewig, 79 Ill. App. 2d 377 (Ill. App. 1967) (test for extras: five Watson elements; clear and convincing proof where needed; extras outside contract)
  • Shields Pork Plus, Inc. v. Swiss Valley Ag Service, 329 Ill. App. 3d 305 (Ill. App. 2002) (contract interpretation and ambiguity guiding intent)
  • Dean v. Rutherford, 49 Ill. App. 3d 768 (Ill. App. 1977) (construction implied warranty of workmanlike performance)
  • Hayes Mechanical, Inc. v. First Industrial, L.P., 351 Ill. App. 3d 1 (Ill. App. 2004) (quasi-contractual recovery limits under contract)
  • Midwest Emergency Associates-Elgin, Ltd. v. Harmony Health Plan of Illinois, Inc., 382 Ill. App. 3d 973 (Ill. App. 2008) (unjust enrichment/quantum meruit under contract)
Read the full case

Case Details

Case Name: Stark Excavating v. Carter Construction Services
Court Name: Appellate Court of Illinois
Date Published: Mar 28, 2012
Citation: 2012 IL App (4th) 110357
Docket Number: 4-11-0357
Court Abbreviation: Ill. App. Ct.