History
  • No items yet
midpage
844 F.3d 1011
8th Cir.
2017
Read the full case

Background

  • Star City School District contracted for a new high school; SBC was general contractor and contracted with ACI to supply metal roofing materials; ACI did not install the roof.
  • The roof leaked from installation; architect and ACI inspectors documented installation defects; SBC issued a 10-year warranty in Feb. 2006 promising ACI would repair or replace materials and SBC would repair workmanship.
  • District took possession after a certificate of substantial completion (Mar. 28, 2005) and used the building; leaks persisted despite repeated repairs by SBC and later by a local contractor (authorized and paid by ACI as a goodwill gesture).
  • SBC ceased repairs, later went bankrupt; District delayed claiming on the performance bond until 2012 (denied) and sued ACI in 2013 alleging fraud, constructive fraud, breach of warranty, breach of contract, and negligence.
  • District court dismissed fraud claims for failure to plead with particularity and granted summary judgment for ACI on remaining claims as barred by Arkansas’s five-year statute of repose; the Eighth Circuit affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether District pleaded actionable fraud/constructive fraud ACI repeatedly promised to repair/replace the roof and concealed deficiencies; those assurances induced reliance Promissory statements about future repairs are not actionable as fraud absent allegation ACI knew promise was false when made; plaintiff failed to plead particularized facts or actual reliance Affirmed dismissal: promises about future acts are not fraud absent factual allegation of intent to deceive; no pleaded actual reliance
Whether plaintiff alleged actual reliance District says it refrained from filing bond claim or suit because of ACI’s assurances ACI says complaint lacks allegations of acts/omissions taken in reliance on alleged misrepresentations Affirmed: complaint failed to allege that District acted or refrained from acting by reason of ACI’s statements
Whether Arkansas five-year statute of repose bars warranty/contract/negligence claims District contends building was never substantially completed and/or warranty claims avoid the repose period ACI argues building was substantially complete in 2005 and statute of repose applies to claims arising from defective construction or repair, including warranty claims tied to installation Affirmed summary judgment: substantial completion occurred in 2005; claims filed in 2013 are time-barred under § 16-56-112(a)
Whether statute of repose was tolled while repairs were attempted or by warranty District invokes repair doctrine/tolling while ACI attempted repairs and cites older case law ACI relies on Arkansas precedent treating § 16-56-112 as a statute of repose that extinguishes causes after five years absent fraudulent concealment; parties cannot toll repose by agreement Affirmed: no evidence of fraudulent concealment; repair attempts do not toll statute of repose

Key Cases Cited

  • Bell Atlantic Corp. v. Twombly, 550 U.S. 544 (pleading must state plausible claim)
  • Farm Credit Servs. of Am. v. Haun, 734 F.3d 800 (9th Cir.?) (standard of review on motion to dismiss)
  • Drobnak v. Andersen Corp., 561 F.3d 778 (fraud pleading requirements under Rule 9(b))
  • Country Corner Food & Drug, Inc. v. First State Bank & Trust Co. of Conway, Ark., 966 S.W.2d 894 (Ark. 1998) (elements of actual fraud under Arkansas law)
  • SEECO, Inc. v. Hales, 22 S.W.3d 157 (Ark. 2000) (definition of actual reliance under Arkansas law)
  • Morrison v. Back Yard Burgers, Inc., 91 F.3d 1184 (8th Cir. 1996) (future promises actionable only if made with knowledge of falsity)
  • Okla Homer Smith Furniture Mfg. Co. v. Larson & Wear, Inc., 646 S.W.2d 696 (Ark. 1983) (purpose and reach of Arkansas statute of repose)
  • Curry v. Thornsberry, 128 S.W.3d 438 (Ark. 2003) (statute of repose extinguishes right of action after prescribed period)
Read the full case

Case Details

Case Name: Star City School District v. ACI Building Systems, LLC
Court Name: Court of Appeals for the Eighth Circuit
Date Published: Jan 6, 2017
Citations: 844 F.3d 1011; 2017 WL 65389; 15-3723
Docket Number: 15-3723
Court Abbreviation: 8th Cir.
Log In
    Star City School District v. ACI Building Systems, LLC, 844 F.3d 1011