History
  • No items yet
midpage
440 F.Supp.3d 1
D.D.C.
2020
Read the full case

Background

  • Dakota Access Pipeline (DAPL) sought an easement to cross under Lake Oahe (Missouri River); the U.S. Army Corps of Engineers issued an Environmental Assessment (EA) and a Mitigated Finding of No Significant Impact (FONSI) and granted the easement in Feb. 2017.
  • Standing Rock, Cheyenne River, Oglala, and Yankton Tribes sued, alleging NEPA and NHPA violations and other claims; litigation produced earlier opinions remanding certain NEPA deficiencies to the Corps.
  • The D.C. District Court previously found the Corps’ no-EIS decision largely compliant but identified three remandable NEPA defects: (1) failure to analyze whether impacts were “highly controversial,” (2) failure to analyze effect of spills on treaty hunting/fishing rights, and (3) inadequate environmental-justice analysis.
  • On remand the Corps responded to extensive expert critiques (from Tribes, EPA, Interior, and consultants) addressing leak-detection reliability, operator safety history, winter-response challenges, and worst-case discharge (WCD) methodology.
  • The Court applied D.C. Circuit guidance (notably National Parks Conservation Ass’n v. Semonite) to assess whether remand responses resolved scientific controversies and whether an EIS is required.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Corps adequately addressed expert critiques so that project is not "highly controversial" under NEPA §1508.27(b)(4) Tribes: Many expert critiques (leak detection, WCD, operator record, winter response) remain unresolved and demonstrate substantial scientific dispute requiring an EIS Corps/Dakota Access: Corps considered and attempted to address comments on remand; prior agency objections do not control; consultation and revised analyses suffice Held: Court finds unresolved, substantive scientific disputes; project is "highly controversial" and Corps must prepare an EIS
Leak-detection system adequacy Tribes: PHMSA and expert data show CPM/SCADA systems have low detection rates; system not designed to detect <1% leaks; slow leaks can persist undetected Corps: DAPL’s CPM (LeakWarn) is "state-of-the-art," capable of 1–3 minute rupture detection; system sensitive to smaller flow changes; training/exercises planned Held: Corps failed to rebut critiques (ignored PHMSA data; relied on applicant assurances); concerns unresolved
Worst-case discharge (WCD) calculation (detection time, shutdown time, adverse conditions) Tribes: WCD understates release by using optimistic detection/shutdown times, omitting prolonged detection, human/equipment failure, and adverse winter conditions Corps: WCD used values from applicant and consults; valves close in ~3.9 min and pumps/controls allow ~9 min shutdown; design accounts for low-temp equipment Held: Corps’ reliance on applicant best-estimates and idealized assumptions does not dispel experts’ criticisms; WCD analysis is unreliable and controversy remains
Operator safety record and its role in risk analysis Tribes: Sunoco/ETP has a poor incident record that should affect spill probability and response assumptions Corps: Many incidents confined to operator property; Corps lacks an alternative methodology showing operator history would change conclusions Held: Corps failed to explain why operator history was excluded from risk analysis; issue unresolved
NHPA claims (mootness / scope of review) Tribes: NHPA violations persist; case fits capable-of-repetition-yet-evading-review exception Corps: Pipeline construction completed; claims moot; no reasonable expectation of recurrence; prior NHPA ruling was correct Held: NHPA claims are moot and would fail on merits if not; Court declines to revive them
Mni Waconi Act breach (Oglala trust duty) Oglala: Corps breached statutory trust duty by not considering impacts to the Oglala Sioux Rural Water Supply System (OSRWSS) Corps: Act’s duties are appropriation-limited; OSRWSS intake is 205 miles downstream; remand addressed water-supply impacts Held: No breach shown; Corps adequately considered OSRWSS and did not render current water supply inadequate
Vacatur of easement during EIS preparation Tribes: Easement should be vacated pending EIS to prevent irreversible harm Corps/Dakota Access: Vacatur is extreme and would disrupt completed construction and operations Held: Court did not vacate immediately; ordered supplemental briefing on vacatur applying Allied-Signal factors before ruling

Key Cases Cited

  • National Parks Conservation Ass'n v. Semonite, 916 F.3d 1075 (D.C. Cir. 2019) (clarified review for when agency must prepare an EIS under the "highly controversial" factor)
  • Grand Canyon Trust v. FAA, 290 F.3d 339 (D.C. Cir. 2002) (any one §1508.27(b) factor can require an EIS)
  • Motor Vehicle Mfrs. Ass'n v. State Farm, 463 U.S. 29 (U.S. 1983) (arbitrary-and-capricious standard for agency action)
  • Baltimore Gas & Elec. Co. v. NRDC, 462 U.S. 87 (U.S. 1983) (NEPA requires consideration of every significant environmental aspect)
  • Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (limited role of courts reviewing agency decisions not to prepare an EIS)
  • Allied-Signal, Inc. v. U.S. Nuclear Regulatory Comm'n, 988 F.2d 146 (D.C. Cir. 1993) (factors to weigh before vacating an agency action)
  • Sierra Club v. U.S. Army Corps of Eng'rs, 803 F.3d 31 (D.C. Cir. 2015) (limits on agency NHPA obligations and scope of effects to be considered)
Read the full case

Case Details

Case Name: Standing Rock Sioux Tribe v. United States Army Corps of Engineers
Court Name: District Court, District of Columbia
Date Published: Mar 25, 2020
Citations: 440 F.Supp.3d 1; Civil Action No. 2016-1534
Docket Number: Civil Action No. 2016-1534
Court Abbreviation: D.D.C.
Log In