History
  • No items yet
midpage
11 A.3d 30
Pa. Commw. Ct.
2010
Read the full case

Background

  • Stambaughs operate a 650-acre dairy farm and constructed an in-ground earthen trench silo for corn silage in September 2005.
  • Trench was unlined, tarp-covered with tires, and located 90–100 feet from two wells on adjacent land.
  • Neighbors complained of malodorous water in October 2005; DEP linked silage leachate to groundwater contamination.
  • DEP ordered removal of silage within 15 days and required replacement water, water treatment, and plans for storage, nutrient management, and erosion/sedimentation; order issued November 4, 2005; no appeal.
  • In 2006, DEP issued notices of violation for inadequate compliance; Stambaughs did not respond; DEP filed a civil penalty action seeking $33,772.
  • Board reduced DEP’s proposed penalties to $18,197; court later vacates and remands for recalculation due to issues with willfulness findings and penalty methodology.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Was willfulness proven for pollution under Section 401? Stambaughs did not knowingly cause pollution; no conscious choice to violate. Board as factfinder may rely on evidence of recklessness and general knowledge of risks. No, willfulness not demonstrated by substantial evidence; remand to recalculate penalties.
Did the Board properly conclude recklessness/willfulness for Section 402 penalties? Delay and failure to move silage were weather-related; no willful delay. Board may rely on evidence of willful delay and inaction. Willfulness not adequately supported; remand for reconsideration of Section 402 penalties.
Was penalty calculation proper for plan-delays under 25 Pa. Code §§ 91.33–91.34 and DEP orders? Delays due to fire and economy should be weighed; explainability and due process require consideration of defenses. Penalties based on late submissions; Board need not detail every justification. Board failed to justify plan-delay penalties; remand to reevaluate penalties with explanations.
Did the Board err by not considering the house fire and economic conditions in calculating penalties? Extraordinary events and economic hardship justified delays; should reduce penalties. General penalties apply; defenses not given weight. Board did not address these defenses; remand to evaluate these factors.

Key Cases Cited

  • Commonwealth v. Shiffler, 583 Pa. 478, 879 A.2d 185 (2005) (definition of willfulness and reasonable interpretive approach to statutory terms)
  • Bethenergy Mines, Inc. v. Department of Environmental Protection, 563 Pa. 170, 758 A.2d 1168 (2000) (agency penalty authority and burdens of proof on penalty assessment)
  • Leeward Construction, Inc. v. Department of Environmental Protection, 821 A.2d 145 (Pa. Cmwlth. 2003) (standard of review for penalties; deference to Board when reasonably related to violations)
Read the full case

Case Details

Case Name: Stambaugh v. Department of Environmental Protection
Court Name: Commonwealth Court of Pennsylvania
Date Published: Dec 10, 2010
Citations: 11 A.3d 30; 2010 Pa. Commw. LEXIS 671; 2010 WL 5025959; 2036 C.D. 2009
Docket Number: 2036 C.D. 2009
Court Abbreviation: Pa. Commw. Ct.
Log In