History
  • No items yet
midpage
220 So. 3d 6
La. Ct. App.
2017
Read the full case

Background

  • Hopkins contracted with St. Bernard Port in 2000 to perform Phase I of a public works project; disputes, alleged abandonment, and counterclaims followed.
  • After offsetting Port damages against sums due Hopkins, a 2011 final judgment awarded Hopkins $101,306.47; the judgment became final in 2013 and the Port did not pay or appropriate funds for it.
  • Hopkins sought a writ of mandamus under La. Rev. Stat. § 38:2191(D) to compel payment from funds appropriated for the contract; the district court granted mandamus in 2016 ordering payment with legal interest.
  • The Port appealed, arguing mandamus cannot be used to collect a money judgment, § 38:2191(D) cannot be applied retroactively to pre-2002 matters, § 38:2191 does not apply to an already-adjudicated judgment, Hopkins failed to satisfy statutory prerequisites (final acceptance, clear lien certificate), no specific appropriation existed, and interest was improper.
  • The appellate court reviewed statutory interpretation de novo and factual findings for manifest error, denied the Port’s exception of no cause of action, and affirmed the mandamus judgment.

Issues

Issue Plaintiff's Argument (Hopkins) Defendant's Argument (Port) Held
Whether mandamus under § 38:2191(D) may be used to secure payment of an adjudicated contract balance § 38:2191(D) allows mandamus to compel payment of sums due under a public contract (including when a judgment fixes the amount) where appropriation exists Mandamus cannot be used to seize public funds to collect a money judgment; constitutional and statutory limits require specific appropriation or other procedure Mandamus is available here; the fact a judgment exists does not preclude § 38:2191(D) relief if statutory requirements are met
Whether § 38:2191(D) (added 2011) applies retroactively to pre-2002 contract/litigation § 38:2191(D) is interpretive/procedural, clarifying availability of mandamus and appropriation requirement, so it may be applied retroactively The 2011 amendment is substantive and cannot be retroactively applied to contracts or suits predating the amendment § 38:2191(D) is interpretive and procedural (not substantive) and may be applied retroactively
Whether § 38:2191 governs enforcement of a pre-existing, final judgment for unpaid contract sums § 38:2191’s purpose is prompt payment of contract obligations; final adjudication of amount does not defeat statutory mandamus remedy The statute is not intended to permit mandamus to collect a money judgment; mandamus only compels ministerial acts, and adjudication involved discretionary determinations § 38:2191 applies; final adjudication of amount is irrelevant if statutory predicates for mandamus are satisfied
Whether Hopkins satisfied § 38:2191 prerequisites (final acceptance, clear lien certificate, abandonment effects) Final payment became due when replacement contractor completed Phase I per contract; attorney-fee prerequisites for formal acceptance do not bar mandamus for final payment Hopkins abandoned work and did not obtain formal final acceptance or clear lien certificate; Port was justified in withholding payment Court found Hopkins was owed a final payment under contract terms despite abandonment; requirements for mandamus here were met
Whether a specific appropriation existed for Hopkins’ contract as required by § 38:2191(D) Funds were appropriated for the Project and for payment of contracts awarded for Phase I, thus satisfying the appropriation requirement Port argues only a general project appropriation existed, not an appropriation specifically for Hopkins’ contract Court found an appropriation was made for the award and execution of the contract and that spending those funds elsewhere does not defeat mandamus relief
Whether judicial interest may be awarded in a mandamus judgment under § 38:2191(D) Interest on sums due under the contract is collectible; courts must award interest on judgments as prayed for or by law Statute does not expressly provide for interest on contract payments; interest is a judgment remedy, not a contract remedy Court awarded judicial (legal) interest, concluding interest is included as sums due under the contract and consistent with judgment interest rules

Key Cases Cited

  • Hoag v. State, 889 So.2d 1019 (La. 2004) (mandamus is an extraordinary remedy limited to compelling ministerial duties)
  • Quality Design & Const., Inc. v. City of Gonzales, 146 So.3d 567 (La. App. 1 Cir. 2014) (upholding mandamus under § 38:2191(D) to enforce payment, including where a judgment exists)
  • Newman Marchive P’ship v. City of Shreveport, 979 So.2d 1262 (La. 2008) (addressing limits on collection from public entities and appropriation requirements)
  • Foster Constr., Inc. v. Town of Richwood, 117 So.3d 607 (La. App. 2 Cir. 2013) (mandamus unavailable where no appropriation was made)
  • Jefferson Lake Sulphur Co. v. Kolb, 76 So.2d 546 (La. 1954) (mandamus may compel payment of judicially determined claims from appropriated funds)
  • Mayeux v. Charlet, 203 So.3d 1030 (La. 2016) (principles for statutory interpretation and applying clear legislative language)
Read the full case

Case Details

Case Name: St. Bernard Port, Harbor & Terminal District v. Guy Hopkins Construction Co.
Court Name: Louisiana Court of Appeal
Date Published: Apr 5, 2017
Citations: 220 So. 3d 6; 2017 La. App. LEXIS 590; 2017 WL 1251087; 2016 La.App. 4 Cir. 0907; NO. 2016-CA-0907
Docket Number: NO. 2016-CA-0907
Court Abbreviation: La. Ct. App.
Log In
    St. Bernard Port, Harbor & Terminal District v. Guy Hopkins Construction Co., 220 So. 3d 6