History
  • No items yet
midpage
Sra International, Inc. v. United States
2014 U.S. App. LEXIS 17680
Fed. Cir.
2014
Read the full case

Background

  • SRA International had provided network support to the FDIC under a GSA GWAC task order (ISC-2) and competed for successor task order ISC-3 under the Alliant GWAC; GSA awarded ISC-3 to CSC.
  • SRA protested to GAO alleging two organizational conflicts of interest (OCIs) arising from CSC’s intended use of subcontractor Blue Canopy, which previously audited FDIC/SRA work.
  • GSA received CSC’s agreement to drop Blue Canopy (curing the "impaired objectivity" OCI), but later issued an FAR 9.503 waiver (post-award) as to any remaining "unequal access to information" OCI; GAO dismissed the protest as academic.
  • SRA filed a post-award bid protest in the Court of Federal Claims seeking to void the OCI waiver, enjoin award of ISC-3 to CSC, and rescission of the task order, arguing the waiver violated FDIC rules and was procedurally inadequate.
  • The Government moved to dismiss for lack of jurisdiction under FASA’s bar on protests “in connection with the issuance or proposed issuance of a task or delivery order” (41 U.S.C. § 4106(f)); the CFC held it had jurisdiction to review the waiver under the Tucker Act (third prong) and sought GAO advisory input; following GAO advisory that the waiver was not arbitrary, the CFC dismissed the case as moot.
  • On appeal, the Federal Circuit held the CFC lacked jurisdiction because SRA’s challenge to the OCI waiver was “in connection with the issuance” of a task order and thus barred by FASA; the court vacated and remanded with instructions to dismiss for lack of jurisdiction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Court of Federal Claims has jurisdiction to review a post-award OCI waiver under the Tucker Act despite FASA’s bar on protests in connection with task-order issuance SRA: Tucker Act’s third prong permits review of alleged statutory/regulatory violations "in connection with a procurement," and a temporally separate, discretionary waiver is not "in connection with" issuance Government: The waiver was made to enable issuance of ISC-3 and thus is "in connection with" the task-order issuance; FASA bars judicial review of such protests Held: FASA’s plain-language bar applies; the challenge to the waiver is "in connection with the issuance" of ISC-3, so CFC lacked jurisdiction and case must be dismissed
Whether temporal separation or discretionary nature of the waiver removes it from FASA’s bar SRA: Post-award timing and discretionary nature make the waiver distinct from the issuance and outside FASA Gov/CSC: Timing and discretion irrelevant; connection to award is dispositive Held: Neither discretion nor post-award timing removes the waiver from FASA’s reach; connection to issuance controls
Whether the relief sought (rescission of task order) affects jurisdictional analysis SRA: Challenge targets the waiver’s validity, not strictly the award Gov: The requested remedy—setting aside the award—shows the protest is about issuance Held: The remedy sought (rescission of the task order) supports conclusion that the protest is in connection with issuance and thus barred
Whether GAO exclusive jurisdiction or advisory opinion alters court’s jurisdiction SRA: Tucker Act jurisdiction for statutory/regulatory claims remains Gov: FASA assigns exclusive GAO jurisdiction for covered task-order protests Held: FASA precludes CFC jurisdiction; GAO role and advisory opinion do not create CFC jurisdiction

Key Cases Cited

  • Distributed Solutions v. United States, 539 F.3d 1340 (Fed. Cir. 2008) (Tucker Act third-prong analysis of procurement-related statutory claims)
  • Blueport Co. v. United States, 533 F.3d 1374 (Fed. Cir. 2008) (standard of review for jurisdictional questions)
  • Billings v. United States, 322 F.3d 1328 (Fed. Cir. 2003) (statutory and regulatory construction reviewed without deference)
  • Mission Essential Personnel, LLC v. United States, 104 Fed. Cl. 170 (Fed. Cl. 2012) (relief sought bears on whether protest is "in connection with" task-order issuance)
  • Unisys Corp. v. United States, 90 Fed. Cl. 510 (Fed. Cl. 2009) (jurisdictional implications informed by requested relief)
  • Global Computer Enterprises v. United States, 88 Fed. Cl. 350 (Fed. Cl. 2009) (post-award modifications and temporal separation considered in jurisdictional analysis)
Read the full case

Case Details

Case Name: Sra International, Inc. v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Sep 15, 2014
Citation: 2014 U.S. App. LEXIS 17680
Docket Number: 2014-5050
Court Abbreviation: Fed. Cir.