History
  • No items yet
midpage
217 N.C. App. 300
N.C. Ct. App.
2011
Read the full case

Background

  • APAC-Atlantic, the prime contractor, obtained a payment bond from Liberty Mutual and Travelers for the Greensboro project.
  • English subcontracted part of the grassing work to Southern Seeding; the subcontract included Note 15 equitable adjustment and Paragraph 7 no damages for delay.
  • Note 15 guaranteed an equitable adjustment for increased costs if delays occurred beyond the July 1, 2007 completion date; Paragraph 7 restricted delays to compensation only if paid by Owner or third parties.
  • The project extended to March 14, 2008 due to multiple supplemental agreements; Southern Seeding sought $194,941.39 for post-July 1, 2007 cost increases.
  • English offered only $2,300 to settle, excluding post-1 July 2007 cost increases; plaintiff sued for breach of contract and for payment bond recovery.
  • Trial court dismissed claims; on appeal, court held Note 15 and Paragraph 7 are distinct and must be interpreted together but not to negate Note 15.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Interpretation of Note 15 vs. Paragraph 7 Note 15 supports equitable adjustment for post-July 2007 costs. Paragraph 7 bars delay damages absent compensation from owner/third party and negates Note 15. Paragraph 7 and Note 15 are distinct; Note 15 permits equitable adjustment notwithstanding Paragraph 7.
Whether plaintiff is entitled to an equitable adjustment under Note 15 Equitable adjustment is available for market-driven post-2007 cost increases. English had no remedy against APAC/NCDOT to obtain such adjustment. Plaintiff is entitled to an equitable adjustment under Note 15; trial court erred.
Liability of the sureties on the payment bond Bond covers damages due to English's breach affecting subcontractors. Bond applies narrowly to labor/materials for the project; breach not within bond terms. Sureties liable; payment bond intended for subcontractors and laborers, not limited to direct contract terms.

Key Cases Cited

  • Int'l Paper Co. v. Corporex Constructors, Inc., 96 N.C.App. 312 (1989) (contract interpreted as a whole; give effect to all provisions)
  • APAC-Carolina, Inc. v. Greensboro-High Point Airport Auth., 110 N.C.App. 664 (1993) (distinguishes delay damages from unit price adjustments)
  • Symons Corp. v. Ins. Co. of N. Am., 94 N.C.App. 541 (1989) (payment bond protections for subcontractors/materialmen)
  • Beachcrete, Inc. v. Water St. Ctr. Assocs., L.L.C., 172 N.C.App. 156 (2005) (surety liable to subcontractor under payment bond)
  • Interstate Equip. Co. v. Smith, 292 N.C. 592 (1977) (third-party beneficiary may sue on contractor's bond)
  • Boatwright Distribution & Supply, Inc. v. N. State Mech., Inc., 2010 WL 3464837 (2010) (unpublished; cited for payment bond scope)
Read the full case

Case Details

Case Name: Southern Seeding Service, Inc. v. W.C. English, Inc.
Court Name: Court of Appeals of North Carolina
Date Published: Dec 6, 2011
Citations: 217 N.C. App. 300; 719 S.E.2d 211; 2011 N.C. App. LEXIS 2432; COA11-381
Docket Number: COA11-381
Court Abbreviation: N.C. Ct. App.
Log In
    Southern Seeding Service, Inc. v. W.C. English, Inc., 217 N.C. App. 300