History
  • No items yet
midpage
Southern Electrical Services, Inc. v. City of Houston
355 S.W.3d 319
Tex. App.
2011
Read the full case

Background

  • SES, as Morganti's assignee, sued the City of Houston for breach of contract and for interest under the Prompt Payment Act regarding a central concourse project at Hobby Airport.
  • Morganti awarded a lump-sum contract; SES, a subcontractor, bid based on the City-provided prevailing wage rates and the subcontract incorporated the City–Morganti contract.
  • Document 00812 set minimum prevailing wage rates; Document 00813 amended rates upward; both allowed higher wages but not required payments.
  • City later amended wages to 00813 and offered to reimburse variances; Morganti and SES did not receive wage increases due to the switch, and SES was paid in full under the lump-sum contract.
  • SES sought the difference between the initially certified rates and the correct rates, plus interest; trial court granted summary judgment for the City.
  • On rehearing, the court reaffirmed that SES failed to show damages causally connected to the alleged breach and that the Prompt Payment Act claim failed as a matter of law.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the City breach contract damages proven by SES? SES argues the City provided incorrect wage scales, causing increased costs and damages. City contends no damages were proven or consequential from the wage-scale misstatement. No genuine damages issue; City not liable.
Are SES's alleged damages foreseeably resulting from the City's breach? SES relied on the wrong wage scales in bidding and cost calculations. Wage-rate minimums are not guarantees of payment of higher wages; risks allocated to the contractor. Damages too speculative/not foreseeable; contract allocated cost risk to SES.
Does the contract bar SES's recovery or limit it under the Local Government Code? SES asserts damages are recoverable despite statutory limits. Code provisions together with contract language bar recovery of the claimed damages. Held not to change outcome; damages barred by foreseeability and allocation of risk.
Is SES entitled to relief under the Prompt Payment Act for additional payment due to breach? City's breach justifies interest under the Act on the extra payment. Breach claim lacks merit, so the Prompt Payment Act claim is inapplicable. Prompt Payment Act claim fail as the breach claim failed.

Key Cases Cited

  • Wright v. Christian & Smith, 950 S.W.2d 411 (Tex. App.-Houston [1st Dist.] 1997) (elements of breach of contract required for recovery)
  • City of Dallas v. Villages of Forest Hills, L.P., Phase I, 931 S.W.2d 601 (Tex.App.-Dallas 1996) (damages must be foreseeable and not speculative)
  • A.B.F. Freight Sys., Inc. v. Austrian Import Serv., Inc., 798 S.W.2d 606 (Tex.App.-Dallas 1990) (damages cannot be remote or conjectural)
  • Houston Gulf Coast Bldg. & Constr. Trades Council, 710 S.W.2d 181 (Tex.App.-Houston [1st Dist.] 1986) (prevailing wage rate determinations; finality of rate decisions)
  • United States v. Binghamton Constr. Co., 347 U.S. 171 (1954) (minimum wage requirements assume possibility of higher pay)
Read the full case

Case Details

Case Name: Southern Electrical Services, Inc. v. City of Houston
Court Name: Court of Appeals of Texas
Date Published: Aug 18, 2011
Citation: 355 S.W.3d 319
Docket Number: 01-10-00649-CV
Court Abbreviation: Tex. App.