156 F. Supp. 3d 83
D.D.C.2015Background
- Solenex LLC holds an oil/gas lease (BLM lease) in Montana dating to a 1982 lease and an approved APD in 1985; the APD has been suspended intermittently and continuously since July 15, 1998.
- Multiple federal agencies (BLM, Forest Service, others) have conducted NEPA and NHPA reviews that have delayed final agency action on whether to lift the suspension.
- The administrative review and suspension determination have remained unresolved for ~29 years at the time of the opinion.
- Solenex sued under the Administrative Procedure Act alleging unlawful delay/unreasonably withheld agency action and moved for summary judgment; defendants cross-moved for summary judgment.
- The Court found the 29-year delay unreasonable under the APA but declined to directly order lifting the suspension; instead it imposed a judicially supervised remedy requiring the agencies to submit an expedited schedule.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether agencies unreasonably delayed final action under the APA | Delay of ~29 years is unreasonable and requires relief | Delay justified by complex NEPA/NHPA reviews and ongoing work | Court: Delay is unreasonable under 5 U.S.C. §706(1) (finds 29 years excessive) |
| Appropriate remedy for unreasonable delay | Court should order immediate lifting of the lease suspension | Court should not directly lift suspension; agencies should be allowed to finish reviews | Court: Denies order to lift suspension; directs less intrusive remedy (court-supervised schedule) |
| Form of judicial oversight to compel agency action | Require agencies to set a firm timetable to resolve suspension | Agencies oppose micromanagement and argue progress is near completion | Court: Orders agencies to submit an accelerated schedule within 21 days for court approval and to adhere to it |
| Consequences for noncompliance with schedule | Immediate judicial relief (lift suspension) if agencies fail | Agencies seek flexibility and claim ongoing near-completion status | Court: Requires court approval for schedule changes and explanations for material failures; failure could lead to further judicial relief, potentially lifting suspension |
Key Cases Cited
- Nader v. F.C.C., 520 F.2d 182 (D.C. Cir. 1975) (decades-long agency delay unacceptable; court may order supervised schedule)
- Public Citizen Health Research Group v. Brock, 823 F.2d 626 (D.C. Cir. 1987) (court can compel adherence to agency schedule to cure delay)
- Air Line Pilots Ass’n, Int’l v. C.A.B., 750 F.2d 81 (D.C. Cir. 1984) (court ordered status reports and supervised schedule for agency action)
- MCI Telecommunications Corp. v. F.C.C., 627 F.2d 322 (D.C. Cir. 1980) (judicially supervised schedule appropriate to conclude prolonged agency proceedings)
- In re American Rivers & Idaho Rivers United, 372 F.3d 413 (D.C. Cir. 2004) (six-year agency delay found egregious)
- Public Citizen Health Research Group v. Auchter, 702 F.2d 1150 (D.C. Cir. 1983) (multi-year delays in agency decisionmaking can be unreasonable)
- Muwekma Tribe v. Babbitt, 133 F. Supp. 2d 30 (D.D.C. 2000) (court directed agency to submit schedule for resolution)
- Geneme v. Holder, 935 F. Supp. 2d 184 (D.D.C. 2013) (eight-year delay held unreasonable)
- Han Cao v. Upchurch, 496 F. Supp. 2d 569 (E.D. Pa. 2007) (four-year delay in administrative review presumptively unreasonable)
