History
  • No items yet
midpage
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104
| Tex. | 2010
Read the full case

Background

  • Solar, a general contractor, and TA, the owner, contracted to build a truck stop in San Antonio for about $4 million.
  • Project was substantially complete in August 2000; punch list items remained and liens were filed by Solar and subcontractors.
  • TA terminated Solar for cause and withheld final payment, citing failure to keep the project lien-free and punch-list deficiencies.
  • Solar sued for breach of contract to recover the contract balance; TA counterclaimed for delays and defective work.
  • At trial, damages were awarded to Solar; on appeal, TA argued lien-release affidavit was a condition precedent to final payment and recovery.
  • Texas Supreme Court held the lien-release provision is a covenant, reversed the appellate court, and remanded for proceedings consistent with this opinion.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Is the lien-release provision a condition precedent to recovery? Solar argues no conditional language; provision is covenant. TA argues statute and contract make lien-release a condition precedent. No; provision is a covenant, not a condition precedent.
Does interpretation avoid forfeiture and align with statutory lien scheme? Covenant interpretation avoids forfeiture. Condition precedent interpretation yields forfeiture. Covenant reading avoided forfeiture and aligned with lien statutes.
What is the effect on final payment pending lien resolution? Solar entitled to balance subject to lien release. TA may withhold final payment until lien-release affidavit is provided. Remand for trial to confirm liens are satisfied before final payment.

Key Cases Cited

  • Centex Corp. v. Dalton, 840 S.W.2d 952 (Tex. 1992) (defining condition precedent elements and remedies)
  • Criswell v. European Crossroads Shopping Ctr., Ltd., 792 S.W.2d 945 (Tex. 1990) (absence of conditional language implies covenant, avoid forfeiture)
  • Lesikar Constr. Co. v. Acoustex, Inc., 509 S.W.2d 877 (Tex.Civ.App.-Fort Worth 1974) (all-bills-paid not generally a condition precedent to payment)
  • Hohenberg Bros. Co. v. George E. Gibbons & Co., 537 S.W.2d 1 (Tex. 1976) (interpretation favors promises over forfeiture when ambiguity exists)
  • Landscape Design v. Harold Thomas Excavating, 604 S.W.2d 374 (Tex.Civ.App.-Dallas 1980) (absence of explicit conditional language suggests covenant)
Read the full case

Case Details

Case Name: Solar Applications Engineering, Inc. v. T.A. Operating Corp.
Court Name: Texas Supreme Court
Date Published: Dec 3, 2010
Citation: 327 S.W.3d 104
Docket Number: 06-0243
Court Abbreviation: Tex.