History
  • No items yet
midpage
Snake Steel, Inc. v. Holladay Construction Group, LLC - Concurring
M2019-00322-SC-R11-CV
| Tenn. | Jun 30, 2021
Read the full case

Background

  • Snake Steel (subcontractor) sued Holladay (prime contractor) over withheld retainage tied to the 2200 Charlotte Avenue project.
  • The owner paid retainage to Holladay on May 27, 2015; dispute arose whether Holladay was then required to deposit those funds into a separate, interest-bearing escrow account or merely to pay subcontractors within ten days.
  • At the trial-court hearing Holladay effectively stipulated it had an obligation to place the funds in escrow after receipt; Holladay later acknowledged it “should have complied” with the Prompt Pay Act.
  • The Tennessee Supreme Court did not resolve the statutory-interpretation question because Holladay failed to preserve the issue on appeal.
  • Justice Cornelia A. Clark (joined by two justices) concurred separately to urge the General Assembly to clarify whether prime contractors must escrow owner-paid retainage or instead are only required to remit payments to subcontractors within ten days, given the substantial daily damages for noncompliance.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a prime contractor must deposit retainage received from the owner into a separate interest-bearing escrow account Snake Steel: Holladay was statutorily required to place the retainage into escrow upon receipt Holladay: the Prompt Pay Act can be read to require only that prime contractors pay subcontractors within 10 days (no duty to escrow upon receipt); Holladay had also stipulated below that it failed to escrow Court declined to decide (issue not preserved on appeal)
Whether Holladay preserved its alternative statutory-construction argument for appellate review Snake Steel: Holladay’s stipulation and statements foreclose a new interpretation on appeal Holladay: argued alternative readings of the Act but did not preserve them below Held: argument not preserved/waived; Supreme Court refused to address it

Key Cases Cited

  • Hodge v. Craig, 382 S.W.3d 325 (Tenn. 2012) (explains preservation requirements for appellate review)
  • State v. Marrow, 75 S.W.3d 919 (Tenn. 2002) (statutory segments must be construed together in light of general purpose)
  • In re C.K.G., 173 S.W.3d 714 (Tenn. 2005) (adopt a reasonable construction to harmonize statutes)
Read the full case

Case Details

Case Name: Snake Steel, Inc. v. Holladay Construction Group, LLC - Concurring
Court Name: Tennessee Supreme Court
Date Published: Jun 30, 2021
Docket Number: M2019-00322-SC-R11-CV
Court Abbreviation: Tenn.