2016 Ohio 763
Ohio Ct. App.2016Background
- Smith and Sack entered four written contracts (one per project stage) between 2010–2013 for a stone patio, retaining walls, and a detached boundary wall; payments totaled $52,794.
- Sack completed work before providing a seller-issued HSSA cancellation notice; portions of the patio/upper retaining wall failed and the patio became unusable.
- Smith timely signed and mailed cancellation notices for all four contracts on Feb. 12, 2015 (Sack had supplied notices on Feb. 10, 2015) and demanded refunds; Sack did not refund.
- Smith sued for breach of contract, CSPA violations, and HSSA relief; Sack counterclaimed for the unpaid balance on the final invoice.
- Trial court granted summary judgment for Smith on liability (HSSA applies; Smith timely cancelled; seller may not begin performance during the cancellation period and bears the risk), dismissed the counterclaim, and later held a hearing on the amount of Smith’s refund.
- Final judgment refunded Smith $38,052 (full refunds of three invoices and partial refund of one invoice excluding $14,742 for the detached southern wall that Smith admitted was defect-free).
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether timely cancellation under the HSSA entitles Smith to a refund without proving damages | Smith: timely cancellation under HSSA entitles him to refund of payments; no damages proof required | Sack: setting a "damages hearing" meant Smith needed to prove damages; court should award damages only if proven | Held: Smith elected HSSA remedy and was entitled to a refund without proving damages; the hearing determined refund amount, not to convert remedy to damages |
| Whether the trial court erred by awarding a full or partial refund instead of making equitable offsets for benefit received | Smith: entitled to refund of amounts paid; HSSA has no substantial-performance or unjust-enrichment offset for service contracts | Sack: full refund would unjustly enrich Smith; court should equitably reduce refund for portions of work without defects | Held: HSSA does not require offsets for services begun before cancellation; court properly deducted only for the separate detached wall that was defect-free |
| Whether the court should have excluded payment for patio steps from the refund | Smith: steps were part of unusable patio and therefore part of cancellation refund | Sack: Smith identified no problem with steps; refund should be reduced for them | Held: steps were part of the failed patio; court did not abuse discretion by including their cost in the refund |
Key Cases Cited
- Clemens v. Duwel, 100 Ohio App.3d 423 (2d Dist.) (construction begun before HSSA cancellation period places risk on seller)