History
  • No items yet
midpage
288 P.3d 1063
Utah Ct. App.
2012
Read the full case

Background

  • Feb 2005 Smargons contract to purchase a Park City-area condo from GLP; option payment of $154,900 paid.
  • March 2005 Smargons learned a mechanical room with a large chiller would be across the hall; GLP promised noise mitigation efforts.
  • Smargons paid an additional $154,900 as earnest money and spent about $92,717 on upgrades to the Unit.
  • Aug 9, 2007 walk-through noted noise/vibration from the mechanical room; inspection was cut short and a punch list was not completed.
  • GLP sent three letters (Aug 20, Aug 29, Sept 6, 2007) offering refunds or close, but asserted default and warned of litigation; Smargons sought contract relief.
  • District court granted summary judgment to Smargons, awarding liquidated damages and reliance damages for upgrades; court denied expectancy damages; GLP appealed and this Utah Court of Appeals affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
whether GLP repudiated the contract by inadequate assurances Smargons argue GLP failed to provide adequate assurances GLP argues assurances were adequate or dispute framed as breach by Smargons repudiation found; assurances inadequate as a matter of law
whether damages were correct, including reliance vs expectancy Smargons seek expectancy and reliance damages GLP argues only liquidated damages unless allowed by contract court reasonably awarded reliance damages; modern approach clarifies limits on liquidated damages

Key Cases Cited

  • Bitzes v. Sunset Oaks, Inc., 649 P.2d 66 (Utah 1982) (repudiation: adequacy of assurances analysis guidance)
  • Kaiser‑Francis Oil Co. v. Producer’s Gas Co., 870 F.2d 563 (10th Cir. 1989) (adequacy of assurances; summary judgment standard in fact-intensive questions)
  • Spring Creek Holding Co. v. Shinnihon U.S.A. Co., 943 A.2d 881 (N.J. 2008) (adequacy of assurances context; avoid mere predictions without detail)
  • Brisbin v. Superior Valve Co., 398 F.3d 279 (3d Cir. 2005) (assurances analyzed as ongoing willingness to perform; not adequate where ongoing posture)
  • Reliance Ins. Co. v. Utah Dep’t of Transp., 858 P.2d 1363 (Utah 1993) (Restatement §339 approach to liquidated damages (abrogated by 2012))
  • Commercial Real Estate Inv., LC v. Comcast of Utah II, Inc., 2012 UT 49 (Utah 2012) (abandoned Restatement approach; enforceability reviewed for unconscionability)
Read the full case

Case Details

Case Name: Smargon v. Grand Lodge Partners, LLC
Court Name: Court of Appeals of Utah
Date Published: Oct 25, 2012
Citations: 288 P.3d 1063; 2012 Utah App. LEXIS 314; 2012 UT App 305; 2012 WL 5258953; 20110059-CA
Docket Number: 20110059-CA
Court Abbreviation: Utah Ct. App.
Log In
    Smargon v. Grand Lodge Partners, LLC, 288 P.3d 1063