History
  • No items yet
midpage
956 F.3d 950
7th Cir.
2020
Read the full case

Background

  • Skyrise (subcontractor) submitted bids July 7 and July 19, 2017 to Annex (general contractor) for framing work; Annex sent a Letter of Intent on July 19 indicating it intended to enter into a contract and would provide contract documents.
  • Annex emailed a multi-page Proposed Contract (with detailed general conditions) in August; Skyrise delayed returning it while reviewing; Annex signed the July 19 bid as “Contract exhibit A” on September 22 at Skyrise’s request.
  • Skyrise returned a marked-up version of the Proposed Contract on October 11 with handwritten edits (including material changes to payment terms); Annex never signed the altered draft and later rejected Skyrise’s October 31 expanded proposal.
  • Skyrise sued for breach of contract, promissory estoppel, negligent misrepresentation, violation of the Illinois Consumer Fraud Act, and violation of the Wisconsin Deceptive Trade Practices Act; the district court granted summary judgment to Annex.
  • On appeal, the Seventh Circuit reviewed de novo and applied Wisconsin law to the contract claim (choice-of-law clause) and generally Wisconsin law to the other substantive claims.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a binding contract existed (Sept. 22 or Oct. 11) Sept. 22 signature by Annex created contract; Oct. 11 signed Proposed Contract created contract Sept. 22 signing was only marking the bid as an exhibit; Oct. 11 marked-up return was a material counteroffer that Annex never accepted No contract: Sept. 22 showed no meeting of minds; Oct. 11 was a counteroffer and not accepted
Promissory estoppel Skyrise reasonably relied on Letter of Intent and Annex’s conduct and blocked its schedule Reliance was unreasonable because Letter and negotiations were conditional and meant to be followed by a formal contract No estoppel: reliance was unreasonable; statements were an unenforceable agreement to agree
Negligent misrepresentation / Wisconsin & Illinois consumer-protection claims Annex represented Skyrise had the framing work and induced reliance causing loss Statements and conduct were part of negotiations, not false representations that Skyrise had a firm subcontract Claims fail: no false or deceptive statement proved; only protracted, conditional negotiations shown
Choice of law (Implicit) plaintiff did not contest application of project-law clause Proposed Contract specified governing law; forum’s choice-of-law rules apply Wisconsin law governs the contract claim; Wisconsin law applied to other claims absent a conflict (court did not need to decide Illinois Act applicability)

Key Cases Cited

  • Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986) (summary judgment standard)
  • Skycom Corp. v. Telstar Corp., 813 F.2d 810 (7th Cir. 1987) (objective intent and importance of public/shared expressions for meeting of minds)
  • Hoffman v. Red Owl Stores, Inc., 133 N.W.2d 267 (Wis. 1965) (Wisconsin adoption of promissory estoppel doctrine)
  • C.G. Schmidt, Inc. v. Permasteelisa N. Am., 825 F.3d 801 (7th Cir. 2016) (promissory estoppel is limited; conditional promises are inadequate for reasonable reliance)
  • Disciplinary Hearings Against Nora, 909 N.W.2d 155 (Wis. 2018) (material revisions to an offer convert acceptance into a counteroffer)
  • Dunlop v. Laitsch, 113 N.W.2d 551 (Wis. 1962) (agreements to agree are unenforceable)
  • Cosgrove v. Bartolotta, 150 F.3d 729 (7th Cir. 1998) (conditional or hedged promises do not support promissory estoppel)
Read the full case

Case Details

Case Name: Skyrise Construction Group LLC v. Annex Construction LLC
Court Name: Court of Appeals for the Seventh Circuit
Date Published: Apr 21, 2020
Citations: 956 F.3d 950; 19-1461
Docket Number: 19-1461
Court Abbreviation: 7th Cir.
Log In