History
  • No items yet
midpage
Sierra Club v. United States Army Corps of Engineers
64 F. Supp. 3d 128
D.D.C.
2014
Read the full case

Background

  • Enbridge, a private company, built the 589‑mile Flanagan South (FS) pipeline mostly on private land; federal law does not generally authorize federal oversight of domestic private pipeline construction.
  • The Corps verified ~1,950 water crossings as fitting Nationwide Permit 12 (NWP 12); Corps and BIA issued easements and completed EAs/FONSIs for limited federal land segments. FWS issued a Biological Opinion and incidental take statement after consultation.
  • Plaintiffs (Sierra Club & National Wildlife Federation) sued federal agencies alleging NEPA, CWA, and APA violations, arguing some federal action required an environmental review of the entire pipeline before construction.
  • Procedurally: Court denied a preliminary injunction in an earlier opinion; defendants and intervenor moved to dismiss and moved for summary judgment; some ripeness arguments became moot after Corps/BIA issued easements; claim against PHMSA dismissed for failure to state a claim.
  • Court framed the central question: whether any federal agency (alone or collectively) was required under NEPA to analyze environmental impacts of the entire FS Pipeline prior to construction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Corps' NWP 12 verifications are "major federal actions" triggering NEPA for entire pipeline Corps verifications affected a substantial part of the pipeline and functioned like permits, so NEPA required a pipeline‑wide EIS NWP verifications are permissive confirmations under a general permit regime (not individual permits); Corps lacked the discretion that triggers NEPA Verifications are not "major federal actions" for NEPA; summary judgment for defendants on this claim
Whether FWS Biological Opinion/incidental take statement is a "major federal action" requiring pipeline‑wide NEPA Biological Opinion effectively authorized or enabled construction and thus triggered NEPA FWS opinion is advisory; acting agencies decide how to proceed and the BiOp was not the functional equivalent of a permit here BiOp can sometimes be a major federal action, but on these facts it was peripheral and not the functional equivalent of a permit; summary judgment for defendants
Whether combined federal involvement ("federalization") required a lead agency and pipeline‑wide NEPA Even if individual actions were limited, the aggregate federal actions federalized the project and required a lead NEPA review Federal involvement was limited and did not amount to substantial control or responsibility over the pipeline as a whole Combined actions did not federalize the pipeline; no duty to perform a comprehensive NEPA review or designate a lead agency
Whether Corps violated NWP 12 / CWA / APA by failing to analyze cumulative effects of all crossings pipeline‑wide Corps must assess cumulative effects of all 1,950 crossings together and include that analysis in verifications NWP 12 contemplates regional/watershed cumulative analyses; each district considered cumulative effects within its region and documented mitigation Corps complied with NWP 12 via district‑level cumulative analyses supported by administrative record; no arbitrary or capricious action found

Key Cases Cited

  • Bennett v. Spear, 520 U.S. 154 (U.S. 1997) (Biological Opinions can, in some circumstances, have a coercive effect and function like final agency action)
  • Ramsey v. Kantor, 96 F.3d 434 (9th Cir. 1996) (Biological Opinion and incidental take statement can be the functional equivalent of a permit)
  • Wetlands Action Network v. U.S. Army Corps of Eng’rs, 222 F.3d 1105 (9th Cir. 2000) (distinguishing general permit verifications from individual permits for NEPA purposes)
  • Citizens Against Rails‑to‑Trails v. Surface Transp. Bd., 267 F.3d 1144 (D.C. Cir. 2001) (the key NEPA touchstone is agency discretion)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (U.S. 1983) (agency decisions reviewed for a rational connection between facts and choice; arbitrary and capricious standard)
  • Reliable Automatic Sprinkler Co. v. Consumer Product Safety Comm’n, 324 F.3d 726 (D.C. Cir. 2003) (APA final agency action requirement is not jurisdictional)
Read the full case

Case Details

Case Name: Sierra Club v. United States Army Corps of Engineers
Court Name: District Court, District of Columbia
Date Published: Aug 18, 2014
Citation: 64 F. Supp. 3d 128
Docket Number: Civil Action No. 2013-1239
Court Abbreviation: D.D.C.