midpage
Projects
Sign in to see your projects.
68 F.4th 630
D.C. Cir.
2023
Read the full case

Background

  • FERC certified Mountain Valley Pipeline (MVP) in 2017 under the Natural Gas Act after completing an EIS; Environmental Condition 9 required written authorization that all federal permits be obtained before commencing construction.
  • MVP began construction in 2018 but multiple federal authorizations (BLM/Forest Service, Army Corps, Fish & Wildlife) were vacated by the Fourth Circuit at various times; FERC twice ordered work paused and later allowed partial resumption.
  • State agencies (Virginia, West Virginia) documented numerous erosion and sedimentation control failures, issued violations and fines, and negotiated consent decrees requiring additional controls and monitoring.
  • FERC issued a series of orders: First Extension (extend completion deadline to 2022), Resume Work (allow construction outside a 25-mile exclusion zone), Exclusion Zone Order (allow limited work in parts of exclusion zone), and later modifications; petitions for review followed.
  • The D.C. Circuit upheld FERC on most claims but found FERC’s explanation for declining to prepare a supplemental EIS addressing unexpected sedimentation inadequate; court remanded for further explanation or a supplemental EIS, but denied vacatur of FERC orders.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Mootness of First Extension Order Challenge still live despite expiry because it enabled subsequent extension First Extension expired and was superseded by Second Extension, so claim is moot Moot — First Extension Order challenge dismissed as moot
Jurisdiction under NGA over Exclusion Zone & Second Modification Commission’s Second Modification rendered Exclusion Zone non-final; must file new petition for modification Rehearing was deemed denied by operation of law; Exclusion Zone became final and amendments are part of same order Jurisdiction exists; petition adequately challenges Exclusion Zone as amended
Environmental Condition 9 (must have all federal permits before resuming construction) Condition requires all permits before any further construction resumes Condition applies only to initial commencement; after construction begins FERC can authorize limited resumption while assessing environmental protection FERC’s interpretation reasonable and upheld; resumption outside exclusion zone did not violate Condition 9
Bureaucratic-momentum risk from building up to national forest boundary Partial completion up to forest border will pressure agencies to approve forest crossing Other agencies already rejected alternative routes; limited resumption does not create undue pressure Rejected — FERC reasonably concluded no undue bureaucratic momentum here
Need for supplemental EIS for blasting Widespread blasting is new, significant information not analyzed in EIS Final EIS anticipated blasting impacts; blasting addressed in EIS so supplement unnecessary Rejected — no supplemental EIS required for blasting (EIS already addressed blasting)
Need for supplemental EIS for unexpected sedimentation State enforcement records and fines show sedimentation impacts exceed EIS predictions, so SUPPLEM EIS required Deviations due to unpredictable rainfall and state consent decrees address remaining issues; supplement unnecessary Granted in part — FERC’s explanation was inadequate; remand without vacatur for FERC to prepare SUPPLEM EIS or better explain why one is unnecessary

Key Cases Cited

  • Food & Water Watch v. FERC, 28 F.4th 277 (D.C. Cir. 2022) (context on FERC’s NEPA obligations and pipeline approvals)
  • Allegheny Def. Project v. FERC, 964 F.3d 1 (D.C. Cir. 2020) (deemed denial of rehearing and effect of tolling orders)
  • Marsh v. Oregon Natural Res. Council, 490 U.S. 360 (1989) (standard for when a supplemental EIS is required)
  • Motor Vehicle Mfrs. Ass'n v. State Farm, 463 U.S. 29 (1983) (arbitrary-and-capricious review standard under the APA)
  • Sierra Club v. U.S. Forest Serv., 897 F.3d 582 (4th Cir. 2018) (vacatur of Forest Service and BLM authorizations for MVP)
  • Sierra Club v. U.S. Army Corps of Eng'rs, 909 F.3d 635 (4th Cir. 2018) (vacatur of Corps’ verification under nationwide permit)
  • Stand Up for California! v. U.S. Dep’t of Interior, 994 F.3d 616 (D.C. Cir. 2021) (supplemental EIS required only when new information gives a "seriously different picture")
  • Black Oak Energy, LLC v. FERC, 725 F.3d 230 (D.C. Cir. 2013) (factors for remand with or without vacatur)
  • City of Oberlin v. FERC, 937 F.3d 599 (D.C. Cir. 2019) (disruptive consequences factor in vacatur analysis)
Read the full case

Case Details

Case Name: Sierra Club v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: May 26, 2023
Citations: 68 F.4th 630; 20-1512
Docket Number: 20-1512
Court Abbreviation: D.C. Cir.
Log In