History
  • No items yet
midpage
897 F.3d 582
4th Cir.
2018
Read the full case

Background

  • Mountain Valley Pipeline (MVP) proposed ~303.5 miles of 42-inch interstate natural gas pipeline crossing federal lands, including ~3.6 miles (≈83 acres) of the Jefferson National Forest.
  • FERC served as NEPA lead agency and issued a Final Environmental Impact Statement (EIS) and a Certificate of Public Convenience and Necessity; the Forest Service and BLM were cooperating agencies and adopted the EIS.
  • BLM issued a Record of Decision (ROD) granting a 30-year, 50-foot operational right-of-way (ROW) across Jefferson National Forest, adopting the FERC EIS; Forest Service issued a ROD amending the Jefferson Forest Plan to permit the project on Forest Service land (amendments limited to MVP).
  • Petitioners (Sierra Club et al.) challenged the Forest Service and BLM RODs under NEPA, the National Forest Management Act (NFMA)/2012 Planning Rule, and the Mineral Leasing Act (MLA).
  • The Fourth Circuit vacated both agency RODs and remanded: Forest Service because its adoption of the EIS (sedimentation analysis) and its Planning Rule analysis were arbitrary and capricious; BLM because it failed to apply the MLA requirement favoring use of existing ROWs to the extent practical.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Forest Service lawfully adopted FERC EIS hydrology/sedimentation analysis under NEPA Forest Service adopted an EIS that relied on a flawed Hydrologic Report (containment = 79%, impact threshold = 10%); Forest Service had serious earlier concerns (proposed 48%) and did not explain why concerns were satisfied; thus no independent review or "hard look." Agencies relied on MVP studies and explanations; FERC/BLM/Forest Service reviewed the report and adopted the EIS; subsequent materials supported the chosen metrics. Court: Forest Service acted arbitrarily and capriciously; failed to show independent review or explain abandonment of its 48% concern; remand for explanation/supplemental analysis (esp. regarding TES and reliance on a superseded draft).
Whether EIS/RODs inadequately considered forest impacts and alternatives under NEPA Petitioners say agencies failed to analyze forest fragmentation, interior forest loss, and more nuanced patch/connectivity or visually preferable routes; alternatives analysis was insufficient. Agencies point to detailed EIS analysis of fragmentation, edge effects, visual impacts, and discussion of multiple alternatives weighing tradeoffs (length, crossings, disturbance). Court: Petitioners failed to show the agencies entirely failed to consider forest impacts; agencies provided adequate analysis and explanation; claim denied.
Whether Forest Service complied with NFMA/2012 Planning Rule when amending Jefferson Forest Plan ("directly related" test) Amendments exempt MVP from soil/riparian substantive requirements; Forest Service misapplied §219.13(b)(5) by analyzing only effects and not the purpose of the amendment; soil/water/riparian requirements are directly related and must be applied. Forest Service argued mitigation and project design avoid substantial adverse effects, and applied the Rule consistent with scope/scale of amendment. Court: Forest Service misread the regulation by failing to analyze the amendment's purpose; soil/water/riparian requirements are "directly related" and must be applied; remand for proper application.
Whether BLM complied with MLA obligation to require use of existing rights-of-way "to the extent practical" BLM failed to make a practicability finding favoring existing ROWs and instead adopted NEPA preference for alternatives only if they were "significantly" better; thus BLM did not apply MLA's higher/specific standard. BLM contends its incorporation of the EIS analysis sufficed; it retains discretion and considered collocation but other factors made existing-ROW alternatives impractical. Court: BLM failed to show it determined utilization of existing ROWs was impractical; it "entirely failed to consider an important aspect" required by MLA; vacated and remanded for practicability analysis.

Key Cases Cited

  • Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752 (2004) (NEPA imposes procedural requirements focused on evaluation and disclosure of environmental impacts)
  • Robertson v. Methow Valley Citizens Council, 490 U.S. 332 (1989) (agencies must take a "hard look" at environmental consequences)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins., 463 U.S. 29 (1983) (arbitrary and capricious standard for agency rulemaking)
  • Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87 (1983) (court must ensure agency articulated rational connection between facts and choice)
  • Friends of Back Bay v. U.S. Army Corps of Eng’rs, 681 F.3d 581 (4th Cir. 2012) (judicial review under APA; arbitrary and capricious standard)
  • Hughes River Watershed Conservancy v. Glickman, 81 F.3d 437 (4th Cir. 1996) (cooperating agencies may adopt another agency’s EIS only if it meets adequacy standards and comments are satisfied)
  • Defs. of Wildlife v. N.C. Dep’t of Transp., 762 F.3d 374 (4th Cir. 2014) (description of arbitrary and capricious review)
  • Michigan v. EPA, 135 S. Ct. 2699 (2015) (courts may not supply agency's reasoning; must judge on agency's stated grounds)
Read the full case

Case Details

Case Name: Sierra Club, Inc. v. U.S. Forest Service
Court Name: Court of Appeals for the Fourth Circuit
Date Published: Jul 27, 2018
Citations: 897 F.3d 582; 17-2399; 18-1012; 18-1019; 18-1036
Docket Number: 17-2399; 18-1012; 18-1019; 18-1036
Court Abbreviation: 4th Cir.
Log In
    Sierra Club, Inc. v. U.S. Forest Service, 897 F.3d 582