History
  • No items yet
midpage
Shelton v. Olowosoyo
10 A.3d 45
| Conn. App. Ct. | 2010
Read the full case

Background

  • In 2003–2004, Sheltons planned to renovate and rebuild their Westport home, entering a fixed-price, at-cost contract with Olowosoyo/Starlight for $450,000 (including labor and materials but excluding kitchen, driveway, and architectural fees).
  • Contract originally estimated completion in four months with a detailed payment schedule: $150,000 retainer, $150,000 at framing, $75,000 at drywall, $75,000 at completion.
  • The Shelton loan draw schedule conflicted with the contract terms; the first payment was $90,000 (then $112,000 draw) and the defendants accepted nonconforming payments and continued work.
  • Westport issued a cease-and-desist in December 2004 for permit issues; a building permit was not issued until January 28, 2005.
  • In 2005–2006, the defendants produced multiple amended completion dates (Aug 2, 2005; Dec 31, 2005; May 31, 2006) and the Shelt ons refinanced to provide funds, paying a total of $252,065 by mid-2005; work continued only intermittently.
  • The plaintiffs terminated the contract unilaterally on July 12, 2006; Shoreline Builders completed weatherproofing; the property later sold for $700,000; plaintiffs filed suit seeking contract, CUTPA, veil-piercing, conversion, and unjust enrichment claims; the court ruled that payment terms were modified and completion dates waived, awarding no relief on claims or counterclaims.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the contract's payment terms were modified by the parties' conduct Sheltons contend loan draw schedule modified payment terms Olowosoyo contends original payment terms controlled Yes; modification supported by conduct and mutual assent
Whether completion date provisions were waived Sheltons claim waivers did not apply Olowosoyo argues no waiver Yes; waiver established by continued work and payment deviations
Whether plaintiffs were entitled to damages for breach Sheltons seeking damages for delays Olowosoyo asserts no breach due to waiver No damages; waiver of completion dates foreclosed breach damages
Whether the defendants were unjustly enriched Sheltons paid $229,800; seek $99,750 unjust enrichment Defendants claim lack of cost records precludes recovery Not proven; record lacked cost data; no unjust enrichment award

Key Cases Cited

  • Blacker v. Crapo, 112 Conn.App. 795 (2009) (clear error standard for trial-fact findings; credibility of witnesses; review limited to record)
  • Tsionis v. Martens, 116 Conn. App. 568 (2009) (modification of contracts may be inferred from conduct; mutual assent)
  • Banks Building, Co., LLC v. Malanga Family Real Estate Holding, LLC, 102 Conn.App. 231 (2007) (waiver of contractual completion dates may be inferred from ongoing performance)
  • Breen v. Judge, 124 Conn.App. 147 (2010) (unjust enrichment requires proof of benefit, detriment, and unjust retention; cost-records not provided)
Read the full case

Case Details

Case Name: Shelton v. Olowosoyo
Court Name: Connecticut Appellate Court
Date Published: Nov 30, 2010
Citation: 10 A.3d 45
Docket Number: AC 31413
Court Abbreviation: Conn. App. Ct.