History
  • No items yet
midpage
307 P.3d 449
Or. Ct. App.
2013
Read the full case

Background

  • Catamount Constructors, Inc. (general contractor) contracted Steelwood Construction, Inc. (subcontractor) to supply materials and perform steel and roofing work for a Salem Home Depot project.
  • Catamount terminated the subcontract for convenience under paragraph 18 after Steelwood delivered materials and began work; Steelwood and its suppliers filed liens for unpaid amounts.
  • Catamount paid some suppliers after liens were filed but refused to pay Steelwood for materials and pre-termination work; Steelwood recorded a lien for $369,679.30.
  • Catamount cleaned site debris, hired Panelized Structures to finish the work, and incurred costs toward cleanup and repairs, including locksmith and coordination costs.
  • Contractual documents included a subcontract, purchase order (total $300,000 for materials/work), and a joint check agreement to pay Steelwood and its suppliers jointly.
  • Steelwood sought summary judgment for payment of costs under the contract and the full cost of work performed to termination; the trial court granted summary judgment to Steelwood.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Sufficiency of Steelwood's cost evidence Catamount argued cost substantiation was insufficient; Steelwood relied on Exhibit C and an affidavit. Steelwood contends Exhibit C and affidavits prove actual costs with reasonable certainty; Catamount failed to preserve its challenge. Not addressed on appeal due to preservation failure.
Overhead recovery for Steelwood Catamount argued Steelwood failed to segregate profit and overhead and overruled by lack of certainty. Steelwood claimed overhead was part of actual costs and sufficiently evidenced; preservation issues foreclose review. Not addressed; issue not preserved for review.
Right to offset for defective work after convenience termination Catamount claimed offset for costs to repair Steelwood's alleged defective work was allowed by the contract despite convenience termination. Steelwood denied; termination for convenience forecloses inspection/cure and offsets for defective work. Catamount not entitled to offset for alleged defective work after convenience termination.
Liens and offset under paragraph 32 Catamount argued it could offset lien-related discharge costs under paragraph 32 because liens arose from Steelwood's acts/omissions. Court held liens arose from Catamount's act/omission (nonpayment) and Catamount must bear costs; offset not available. Court correctly refused offset under paragraph 32; Catamount liable for lien-related costs.

Key Cases Cited

  • Yogman v. Parrott, 325 Or 358 (1997) (interpret contracts by examining text in context; ambiguity resolved with extrinsic evidence if needed)
  • Paragon Restoration Group, Inc. v. Cambridge Sq. Condominiums, 839 NYS2d 658 (2007) (emphasizes that no opportunity to correct defects defeats offset after convenience termination)
  • Tishman Contr. Corp. v. City of New York, 643 NYS2d 589 (1996) (discusses conditions under which offsets for defective work may be denied after convenience termination)
  • Lisbon Contractors, Inc. v. United States, 828 F2d 759 (Fed. Cir. 1987) (addresses government termination for convenience and deductions for defective work)
Read the full case

Case Details

Case Name: Shelter Products, Inc. v. Steelwood Construction, Inc.
Court Name: Court of Appeals of Oregon
Date Published: Jul 3, 2013
Citations: 307 P.3d 449; 257 Or. App. 382; 10C20285; A148959
Docket Number: 10C20285; A148959
Court Abbreviation: Or. Ct. App.
Log In
    Shelter Products, Inc. v. Steelwood Construction, Inc., 307 P.3d 449