History
  • No items yet
midpage
Sheet Metal Workers International Ass'n Local Union No. 27 v. E.P. Donnelly, Inc.
737 F.3d 879
| 3rd Cir. | 2013
Read the full case

Background

  • Egg Harbor Township funded a public works project with a PLA requiring signatories to be bound; Carpenters and Sheet Metal were involved through Donnelly and Sambe as prime/subcontractors.
  • Donnelly, a roofing subcontractor, signed the PLA but later did work for Carpenters (unsignatory to PLA) under Carpenters’ CBA, triggering a jurisdictional dispute.
  • Sheet Metal protested the Carpenters’ roofing work; Donnelly and Carpenters threatened picketing, prompting arbitration under Article 10 of the PLA and an Aiges award granting the work to Sheet Metal.
  • Donnelly and Sambe challenged the LJAB decision in NJ state and federal forums; the Board issued a Dec 31, 2007 Section 10(k) order awarding the work to Carpenters, conflicting with Sheet Metal’s 301 suit.
  • Sheet Metal’s 301 suit sought damages and enforcement of the Aiges award; the Board later held Sheet Metal’s suit violated §8(b)(4)(ii)(D) by continuing the suit after the 10(k) order and required withdrawal of the suit against Donnelly.
  • District Court granted Sheet Metal breach of contract damages against Donnelly and Sambe; the Board cross-petitioned for enforcement, and this court reviews Board decisions de novo on law and for substantial evidence on factual findings.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Board had jurisdiction under §10(k) to resolve the PLA dispute Sheet Metal argues no agreed-upon voluntary method existed to resolve the dispute, so Board jurisdiction should apply. Donnelly/Carpenters contend an agreed method existed via the PLA, negating §10(k) jurisdiction. Board had jurisdiction; no effective voluntary dispute mechanism existed under the PLA for this dispute.
Whether Sheet Metal violated §8(b)(4)(ii)(D) by maintaining the §301 suit after the 10(k) award Sheet Metal seeks damages and enforcement of a PLA/arbitration award, not the disputed work itself. Maintenance of the 301 suit after the 10(k) order conflicts with the Board’s award and is illegal under §8(b)(4)(ii)(D). Gundle II controls; maintaining the §301 suit to recover damages against the employer who made the assignment violates §8(b)(4)(ii)(D).
Whether Gundle II governs the outcome and whether damages against Donnelly were properly reversed Sheet Metal urges treating all contract-damage suits the same as in Gundle II. Board/Sheet Metal argue that Gundle II applies to damages against the assigning employer, not to non-assigning contractors. Gundle II controls; the Board’s interpretation prohibiting the 301 suit for damages against the assigning employer is reasonable and enforceable.
Whether the Aiges arbitration award should have been vacated due to the Board’s 10(k) decision Aiges award should be enforceable independently of the Board’s later 10(k) ruling. Carey v. Westinghouse implies Board rulings take precedence; the 10(k) decision nullifies the conflicting arbitration. The Aiges award must be vacated for conflicting with the Board’s 10(k) decision.
Whether the district court erred in granting summary judgment on contract liability against Sambe Sambe breached the PLA by failing to assure Donnelly’s compliance and by allowing the Carpenters’ assignment. Sambe contends the contract language is ambiguous and material facts exist about Sambe’s role in assuring compliance. Summary judgment was improper; issues of contract interpretation and material facts survive against Sambe, requiring remand.

Key Cases Cited

  • Carey v. Westinghouse Elec. Corp., 375 U.S. 261 (1964) (Board precedence over arbitration rulings; supremacy of Board)
  • Bill Johnson’s Restaurants, Inc. v. NLRB, 461 U.S. 731 (1983) (improper-motivation and illegal-objective exceptions under §8(b)(4)(ii)(D))
  • Gundle II, Local 30 v. Gundle Lining Constr. Corp., 1 F.3d 1426 (3d Cir. 1993) (illegal-objective §8(b)(4)(ii)(D) where §10(k) order conflicts with §301 suit)
  • Gundle I, Local 30 v. Gundle Lining Constr. Corp., 939 F.2d 119 (3d Cir. 1990) (injunction standards under §10(l); improper-motivation analysis pre-10(k))
  • Gundle III, United Union of Roofers, Local Union No. 30 v. Gundle Lining Constr. Corp., 1 F.3d 1429 (3d Cir. 1993) (confirms Board interpretation of §10(k) precedence over §301 actions)
  • Local 1291, Int’l Longshoremen’s Ass’n v. Local 1291, 368 F.2d 107 (3d Cir. 1966) (work-rights and compensation framework in jurisdictional disputes)
  • Re Recon Refractory & Constr. Inc. v. NLRB, 424 F.3d 980 (9th Cir. 2005) (three-factor test for §10(k) jurisdiction)
Read the full case

Case Details

Case Name: Sheet Metal Workers International Ass'n Local Union No. 27 v. E.P. Donnelly, Inc.
Court Name: Court of Appeals for the Third Circuit
Date Published: Dec 13, 2013
Citation: 737 F.3d 879
Docket Number: 18-2887
Court Abbreviation: 3rd Cir.