History
  • No items yet
midpage
Shaw Construction, LLC v. United Builder Services, Inc.
2012 COA 24
| Colo. Ct. App. | 2012
Read the full case

Background

  • HOA alleges construction defects in a multi-phase Roslyn Court condo project built by Shaw; Shaw hired United Builder Services and MB Roofing as subcontractors.
  • Project consisted of 3 phases with a final certificate of occupancy (CO) for the last building issued March 10, 2004; architect certified completion on June 8, 2004.
  • HOA sent a notice of claim under CDARA on May 15, 2007; HOA filed suit January 21, 2009, adding Shaw in 2010; Shaw served its CDARA notice of claim on subcontractors the following day.
  • Subcontractors moved for summary judgment arguing the six-year CDARA repose had run; Shaw argued substantial completion occurred at June 8, 2004 per architect’s certification.
  • Trial court held substantial completion occurred at final CO (March 10, 2004), rejected tolling under section 805, and entered summary judgment for subcontractors; this interlocutory appeal followed.
  • Court holds that the last-building improvement is the trigger for repose and that tolling under 805 does not toll subcontractors absent notice to them.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether substantial completion is a matter of law or fact. Shaw says disputed facts exist about tolling and completion. Substantial completion is a question of law based on undisputed facts. Substantial completion is a question of law.
Whether tolling under CDARA §13-20-805 tolls claims against subcontractors lacking notice. Section 805 tolls all related claims when a notice is sent to any construction professional. Section 805 tolling should be limited to those who receive notice; others are not tolled. Shaw's claims against subcontractors were not tolled.
What constitutes the 'improvement' for the statute of repose in a multi-phase project. Improvement means the entire project; repose runs after whole project completion. Improvement can be a discrete component, here the last building. The last building is an improvement for repose purposes.
When repose accrues for the subcontractors' claims in this project. Repose may be triggered later by architect certification. Repose starts with completion of the discrete improvement (last building). Repose began no later than March 10, 2004, at final CO for the last building.

Key Cases Cited

  • Homestake Enters., Inc. v. Oliver, 817 P.2d 979 (Colo.1991) (sprinkler as improvement in larger project)
  • Stanske v. Wazee Elec. Co., 722 P.2d 402 (Colo.1986) (indicator light as improvement in electrical system)
  • Anderson v. M.W. Kellogg Co., 766 P.2d 640 (Colo.1988) (definition of improvement and permanence in project context)
  • Two Denver Highlands Ltd. P'ship v. Stanley Structures, Inc., 12 P.3d 819 (Colo.App.2000) (distinguishing between limitations periods and repose; improvement concept)
  • CLPF-Parkridge One, L.P. v. Harwell Invs., Inc., 105 P.3d 658 (Colo.2005) (CDARA legislative history and purpose guiding interpretation)
Read the full case

Case Details

Case Name: Shaw Construction, LLC v. United Builder Services, Inc.
Court Name: Colorado Court of Appeals
Date Published: Feb 2, 2012
Citation: 2012 COA 24
Docket Number: No. 11CA2351
Court Abbreviation: Colo. Ct. App.