History
  • No items yet
midpage
Sewell v. Sewerage & Water Board of New Orleans
697 F. App'x 288
5th Cir.
2017
Read the full case

Background

  • The Sewerage and Water Board of New Orleans (SWB) and U.S. Army Corps of Engineers (Corps) co-sponsored the federally funded Southeast Louisiana (SELA) Drainage Project; plaintiffs own property in Uptown New Orleans and sued SWB for damage from construction.
  • SWB filed third-party claims against three contractors (B&K, Boh Bros., Cajun Constructors), who removed the cases under the federal officer removal statute, 28 U.S.C. § 1442(a)(1).
  • Contractors moved for summary judgment asserting government-contractor immunity under Boyle; the district court heard argument, granted SWB 30 additional days for discovery under Fed. R. Civ. P. 56(d), but later granted summary judgment for the contractors.
  • The district court found the Corps had approved reasonably precise specifications and meaningfully reviewed plans, satisfying Boyle’s first prong; it concluded the Corps was the primary decisionmaker for critical design features.
  • The district court declined supplemental jurisdiction over remaining state-law claims and remanded those claims to state court; the Fifth Circuit affirmed both the summary judgment and the remand.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether removal under §1442 was proper Implied challenge to federal removal (procedural) Contractors removed under federal-officer statute Removal not reversed on appeal (procedural posture preserved)
Whether district court abused discretion on discovery / Rule 56(d) SWB: discovery time too brief; summary judgment premature without more discovery Contractors: SWB had ample time and produced minimal timely discovery No abuse of discretion; court reasonably managed schedule and granted extra 30 days; summary judgment not premature
Whether Boyle first prong (government-approved reasonably precise specifications) satisfied SWB: specs lacked detail for certain materials; Corps may have delegated review to SWB Contractors: Corps prepared, reviewed, and approved extensive, specific plans and specs, exercising control over critical design choices First Boyle prong met: Corps approved reasonably precise specifications and was the primary decisionmaker on critical features; summary judgment affirmed
Whether remand of pendent state-law claims was proper SWB: (implicit) preferred federal adjudication? District court: discretionary to remand once federal claims gone Remand was within district court’s discretion; affirmed

Key Cases Cited

  • Boyle v. United Techs. Corp., 487 U.S. 500 (1988) (establishes government-contractor immunity three-prong test)
  • Kerstetter v. Pac. Sci. Co., 210 F.3d 431 (5th Cir. 2000) (applying Boyle test)
  • In re Katrina Canal Breaches Litig., 620 F.3d 455 (5th Cir. 2010) (discusses government approval and precision of specifications)
  • Trevino v. Gen. Dynamics Corp., 865 F.2d 1474 (5th Cir. 1989) (government must exercise discretion over critical design choices)
  • Fed. Ins. Co. v. Singing River Health Sys., 850 F.3d 187 (5th Cir. 2017) (abuse-of-discretion standard for discovery rulings)
  • Crosby v. La. Health Serv. & Indem. Co., 647 F.3d 258 (5th Cir. 2011) (standard for reviewing discovery-related decisions)
  • Jones v. Roadway Express, Inc., 936 F.2d 789 (5th Cir. 1991) (district court discretion to remand pendent state-law claims)
Read the full case

Case Details

Case Name: Sewell v. Sewerage & Water Board of New Orleans
Court Name: Court of Appeals for the Fifth Circuit
Date Published: Aug 28, 2017
Citation: 697 F. App'x 288
Docket Number: 17-30089 Summary Calendar
Court Abbreviation: 5th Cir.