History
  • No items yet
midpage
Seven Seas Shipchandlers LLC
ASBCA No. 60602
| A.S.B.C.A. | Oct 25, 2016
Read the full case

Background

  • Seven Seas Shipchandlers (appellant) performed five firm‑fixed‑price supply contracts for Kandahar Air Field in 2009 and submitted invoices in June 2009.
  • The government’s payment office disbursed the contract funds in Afghan cash to a third party (Muhammad Qahir); the money never reached Seven Seas and was later treated as stolen.
  • Seven Seas filed certified CDA claims after asserting it was not paid; the contracting officer denied them; the Board (Seven Seas I) later sustained those appeals and awarded $240,579.90 plus CDA interest.
  • Because the parties disputed whether Seven Seas had already been paid (government argued apparent authority of Qahir), payment was delayed and the dispute ripened into CDA litigation that lasted years.
  • After the Board decision, the government paid the principal plus CDA interest in December 2015; Seven Seas then submitted a separate claim for Prompt Payment Act (PPA) interest and sought additional PPA interest, including on CDA interest and for an extended accrual period.
  • The contracting officer issued no final decision on the PPA claim; Seven Seas appealed to the ASBCA, which considered whether the PPA exception for disputes barred PPA interest.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether PPA interest is due when payment delay resulted from a dispute over payment amount Seven Seas: PPA requires interest from 30 days after invoice; this was an undisputed amount not paid Gov: PPA excludes interest when delay is due to a dispute over payment amount or contract compliance Held: Delay was caused by a dispute over amount (who bore theft risk); PPA exception applies; no PPA interest due
Whether PPA interest may accrue beyond the date a CDA claim was filed or for more than one year Seven Seas: sought PPA interest from June 2009 and continuing beyond payment date, including interest on CDA interest Gov: PPA statutorily limits accrual to date CDA claim filed or one year max Held: PPA limits accrual to CDA‑claim date or one year; Seven Seas cannot accrue the extended amount claimed
Whether ambiguous statutory language requires construing PPA against the government Seven Seas: invoked canons (cites Heth, Mesa Air) to argue ambiguity and contra‑government construction Gov: cited statutory text, regs, and fact pattern showing dispute exception controls; cited cases inapposite Held: Court found cases cited inapposite; PPA interpretation clear here—no ambiguity supporting plaintiff
Whether government acted in bad faith by delaying payment processing after Board decision Seven Seas: alleged bad faith for 8‑month delay and failure to pay PPA interest Gov: refusal to pay PPA interest was lawful; government paid CDA interest to compensate processing time Held: No bad faith; refusal lawful under PPA exception and CDA interest provided compensation

Key Cases Cited

  • United States v. Heth, 7 U.S. (3 Cranch) 399 (1806) (addressed retroactivity; court found it inapposite to PPA interpretation)
  • Mesa Air Group, Inc. v. Dep’t of Transportation, 87 F.3d 498 (D.C. Cir. 1996) (concerned contract/regulatory status of subsidy agreements; court found it inapposite here)

Outcome: Appeal denied; Seven Seas not entitled to PPA interest.

Read the full case

Case Details

Case Name: Seven Seas Shipchandlers LLC
Court Name: Armed Services Board of Contract Appeals
Date Published: Oct 25, 2016
Docket Number: ASBCA No. 60602
Court Abbreviation: A.S.B.C.A.