History
  • No items yet
midpage
Servant Health, LLC v. United States
21-1373
Fed. Cl.
Aug 5, 2022
Read the full case

Background

  • In early 2021 the VA issued solicitations for "on-hand" nitrile exam gloves requiring delivery to designated DLA warehouses within 45 days; solicitations forbade substitutions, required OEM/distributor documentation, and warned failure to meet the deadline could result in termination for cause.
  • Servant Health and Transcendence each were awarded 50 million‑glove contracts; Noble was awarded 25 million; awards were based on specific brands/MPNs and pre‑award technical vetting of submitted documentation.
  • Transcendence made no deliveries and, days before its deadline, notified the VA it could not deliver and proposed substitute brands and a lengthy extension; Servant and Noble made partial, unapproved deliveries of differently packaged/sourced gloves and sought extensions or offered substitutes.
  • The VA issued show‑cause/cure notices (as appropriate) and terminated all three contracts for default on grounds of non‑delivery/repudiation and unapproved substitution; plaintiffs sued to convert the terminations to convenience and recover damages.
  • The court reviewed cross‑motions for summary judgment and held the VA’s terminations were proper: plaintiffs failed to timely deliver, did not establish excusable delay, and the VA was not required to accept post‑award substitutes or breach its implied duty of good faith.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Validity of default terminations (non‑delivery/repudiation) Plaintiffs: terminations improper; some argued lack of cure (Transcendence) or insufficient cure time (Noble) Gov: plaintiffs missed firm 45‑day deadlines, failed to deliver contracted items, and repudiated obligations by offering substitutes Court: Terminations upheld — Transcendence/Servant in default; Noble repudiated; no abuse of CO discretion
Excusable delay under FAR 52.212‑4(f) Plaintiffs: international shipping delays and pandemic (e.g., Suez Canal blockage) excused late performance Gov: delays were foreseeable and resulted from plaintiffs’ choices to source overseas and secure stock post‑award; contractors bore responsibility Court: Plaintiffs failed to prove delays were beyond their control or without fault; excusable delay not shown
Acceptance of post‑award product substitutions Plaintiffs: substitutes were functionally equivalent or same OEM; VA should have accepted them Gov: awards were for specific vetted brands/MPNs/packaging; solicitations forbade substitutions and required pre‑award vetting Court: VA not required to accept unvetted post‑award substitutes; contracts entitled government to exactly what it contracted for
Implied duty of good faith & sufficiency of notices (cure/show cause) Plaintiffs: VA acted in bad faith by not accommodating substitutes/extending time; Transcendence argued lack of cure notice Gov: VA clearly communicated 45‑day, no‑substitution rule and reasonably terminated; cure notice not required where time left inadequate or contractor already repudiated Court: No breach of implied duty; no bait‑and‑switch; cure notice rule inapplicable or unnecessary given timing and repudiation

Key Cases Cited

  • Gen. Injectables & Vaccines, Inc. v. Gates, 519 F.3d 1360 (Fed. Cir. 2008) (failure to make timely delivery establishes prima facie default; burden shifts to contractor to prove excusable delay)
  • McDonnell Douglas Corp. v. United States, 323 F.3d 1006 (Fed. Cir. 2003) (court reviews default terminations and surrounding facts; agency discretion reviewed for arbitrariness)
  • McDonnell Douglas Corp. v. United States, 182 F.3d 1319 (Fed. Cir. 1999) (termination for default must be related to contract performance)
  • Franconia Associates v. United States, 536 U.S. 129 (2002) (contractor’s renunciation before performance date can ripen into breach if promisee elects to treat it as such)
  • Lisbon Contractors, Inc. v. United States, 828 F.2d 759 (Fed. Cir. 1987) (government bears initial burden to show contractor was in default)
  • Nuclear Research Corp. v. United States, 814 F.2d 647 (Fed. Cir. 1987) (contracting officer must determine termination is in government’s best interest)
  • Precision Pine & Timber, Inc. v. United States, 596 F.3d 817 (Fed. Cir. 2010) (limits of implied duty of good faith—no expansion beyond express contract terms)
  • Metcalf Construction Co. v. United States, 742 F.3d 984 (Fed. Cir. 2014) (implied duty cannot alter contractually allocated risks and benefits)
  • J.L. Malone & Associates, Inc. v. United States, 879 F.2d 841 (Fed. Cir. 1989) (Government entitled to obtain precisely what it contracts for)
  • United States v. Brooks‑Callaway Co., 318 U.S. 120 (1943) (contractor cannot rely on listed excuse clauses when its own choices caused the risk)
Read the full case

Case Details

Case Name: Servant Health, LLC v. United States
Court Name: United States Court of Federal Claims
Date Published: Aug 5, 2022
Docket Number: 21-1373
Court Abbreviation: Fed. Cl.