History
  • No items yet
midpage
148 Conn. App. 728
Conn. App. Ct.
2014
Read the full case

Background

  • Sean O’Kane (architect) contracted in Dec. 2000 to provide architectural services for renovation of two adjoining houses owned by Goran and Melinda Puljic; construction by a third party (Rose) began Oct. 2001.
  • O’Kane submitted 23 invoices; defendants paid 1–17 but not 18–23 totaling $92,201.35 for services dated July–Dec. 2002 (no invoices after Dec. 31, 2002).
  • O’Kane sued in 2010 (service June 29, 2010) alleging breach of contract and unjust enrichment; defendants pleaded statute of limitations (Conn. Gen. Stat. § 52-576) and laches.
  • Trial was bifurcated to decide the special defenses first; the trial court held the breach of contract claim time-barred and dismissed unjust enrichment on laches grounds.
  • O’Kane appealed, arguing (1) continuous representation/continuous-performance tolling of the six-year statute, (2) a standstill agreement tolled the limitations period, and (3) laches should not bar unjust enrichment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether § 52-576 barred breach-of-contract claim (continuous representation/course of conduct) Continuous representation or continuous performance delayed accrual until project completion (cert. of occupancy Sept. 25, 2005) Contract billed monthly; invoices due on receipt/15 days; accrual occurs when each invoice became past due in 2002–2003 Court affirmed: statute barred breach claim; continuous representation doctrine not applicable here
Whether a standstill agreement tolled limitations until arbitration resolved (Jan. 2007) Parties agreed not to sue each other until defendants’ dispute with Rose was resolved, tolling limitations No credible evidence of a standstill; withdrawn pleading is not a binding admission Court affirmed: no standstill agreement proved; trial court’s credibility findings upheld
Whether unjust enrichment claim was barred by laches Laches should not defeat equitable unjust enrichment claim against Goran if he was not a contracting party Delay prejudiced defendants; trial court computed prejudice using potential contractual damages Reversed in part and remanded: trial court used incorrect prejudice standard; laches issue must be reevaluated on remand
Whether Goran was a party to the written contract (impacting unjust enrichment claim) Goran was not a signatory and thus unjust enrichment claim against him is available Contract addressed to "Mr. & Mrs. G. Puljic" and factual indicators might show he was a party Remand for trial court to find fact; if Goran was a party, unjust enrichment barred by statute; if not, evaluate laches anew

Key Cases Cited

  • DeLeo v. Nusbaum, 263 Conn. 588 (Conn. 2003) (adopted a limited continuous representation tolling rule for attorney malpractice in litigation)
  • Gaylord Hospital v. Massaro, 5 Conn. App. 465 (Conn. App. 1985) (where services form a single, indivisible continuous course, accrual may be delayed until completion)
  • I. Rosenfield v. David Marder & Assocs., LLC, 110 Conn. App. 679 (Conn. App. 2008) (discussion of accrual and when a cause of action is complete)
  • Dreier v. Upjohn Co., 196 Conn. 242 (Conn. 1985) (withdrawn pleadings may be considered evidential admissions)
  • Piteo v. Gottier, 112 Conn. App. 441 (Conn. App. 2009) (discussing limits of DeLeo and continuous representation doctrine)
Read the full case

Case Details

Case Name: Sean O'Kane A.I.A. Architect, P.C. v. Puljic
Court Name: Connecticut Appellate Court
Date Published: Mar 18, 2014
Citations: 148 Conn. App. 728; 87 A.3d 1124; 2014 WL 928697; 2014 Conn. App. LEXIS 98; AC35245
Docket Number: AC35245
Court Abbreviation: Conn. App. Ct.
Log In