History
  • No items yet
midpage
Scott Timber Co. v. United States
2012 U.S. App. LEXIS 18659
| Fed. Cir. | 2012
Read the full case

Background

  • Timber-harvesting contracts Pigout, Jigsaw, and Whitebird were awarded to Scott in 1999 for 2000–2003 performance.
  • Forests Service suspended contracts to comply with environmental litigation and Northwest Forest Plan requirements.
  • Oregon Natural litigation claimed Forest Service violated plan by not conducting wildlife surveys; settlement required continued suspensions pending surveys.
  • Surveys eventually completed (Pigout 2001; Jigsaw/Whitebird 2000) but suspensions lingered due to related litigation (Umpqua Watersheds) and other environmental challenges.
  • Claims Court found government liable for breach of implied duty of good faith and fair dealing and awarded damages including Roseburg through pass-through and Scott’s own damages.
  • We reverse, finding no liability on the asserted duties and not awarding damages for several components.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether failure to inform Scott of Oregon Natural risks breached the implied duty Scott Timber argues pre-award notice breached duty. United States contends no pre-contract duty existed. No pre-contract duty; no breach established.
Whether continued suspensions under settlement/order breached implied duty Scott contends continued suspensions violated duty to act reasonably. Government asserts suspension authorized to complete surveys under settlement/order. Suspensions valid; no breach found.
Whether government delays in completing surveys violated implied duty Delays unduly lengthened suspensions and harmed Scott. Actions during surveys not specifically targeted and did not reappropriate contract benefits. No breach of implied duty; not reasonably actionable.
Whether Roseburg’s damages could be recovered as pass-through Roseburg’s losses recoverable via pass-through claim. Contract did not require processing by Scott; Roseburg not subcontractor; no pass-through. Pass-through claim rejected; Roseburg damages not recoverable.
Whether Scott could recover replacement costs and lost profits as damages Delay caused damages including lost profits and replacement costs. Partial breach rules limit damage types; profits and replacement costs disallowed. Lost profits disallowed; replacement costs barred; overall damages reversed.

Key Cases Cited

  • Scott Timber Co. v. United States, 333 F.3d 1358 (Fed. Cir. 2003) (reasonableness standard for suspensions under contract clause C6.01; precludes breach finding on unreasonable suspensions if not unreasonable as a matter of fact)
  • Precision Pine & Timber, Inc. v. United States, 596 F.3d 817 (Fed. Cir. 2010) (duty during suspensions not breached when actions not targeted or reappropriating contract benefits)
  • Hercules Inc. v. United States, 24 F.3d 188 (Fed. Cir. 1994) (superior knowledge doctrine requires government awareness of contractor lack of knowledge)
  • Giesler v. United States, 282 F.3d 864 (Fed. Cir. 2000) (superior knowledge framework for disclosure of information impacting contract performance)
  • Int’l Tech. Corp. v. Winter, 523 F.3d 1341 (Fed. Cir. 2008) (pass-through doctrine and subcontractor damages considerations)
  • Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268 (Fed. Cir. 2008) (damages framework for partial breach and timing of performance)
Read the full case

Case Details

Case Name: Scott Timber Co. v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Sep 5, 2012
Citation: 2012 U.S. App. LEXIS 18659
Docket Number: 2011-5092
Court Abbreviation: Fed. Cir.