History
  • No items yet
midpage
462 P.3d 822
Utah Ct. App.
2020
Read the full case

Background

  • Seller (Scott Anderson Trucking) told Buyer (Nielson Construction) it had a pile of rotomill (about 12,000–15,000 tons) and would sell at $25/ton; Buyer’s rep later emailed: “we will need 12000 tons of Rotomill… will pay you $25.00 a ton.”
  • Buyer knew the pile’s location and had opportunity to inspect but did not examine it until at least 16 months later.
  • In Sept. 2015 Buyer used rotomill from another source and informed Seller it rejected Seller’s rotomill as unsatisfactory; thereafter Seller’s rotomill had no market.
  • Seller sued for breach of contract; both parties moved for summary judgment.
  • District court held there was an enforceable contract for 12,000 tons at $25/ton, Buyer’s rejection/repudiation came too late under the UCC, and entered judgment for Seller (principal $300,000 plus interest).
  • Buyer paid the judgment amounts while expressly reserving its right to appeal; the appellate court held the appeal was not moot and affirmed the district court.

Issues

Issue Plaintiff's Argument (Buyer) Defendant's Argument (Seller) Held
Was there an enforceable contract? Email was a first offer or counteroffer (no mutual assent) so no binding contract. Parties’ communications and conduct (email specifying 12,000 tons and $25/ton) established a UCC sale. Court: UCC governs; Buyer failed to grapple with UCC; enforceable contract existed for 12,000 tons at $25/ton.
Did Buyer properly repudiate or reject the goods? Buyer had good cause to terminate and did so when it rejected the rotomill in 2015. Rejection was untimely; Buyer should have inspected and rejected sooner—UCC requires seasonable notice. Court: Rejection/repudiation was untimely as a matter of law (>=16 months); Buyer barred from remedy.
Was the contract a requirements contract limiting quantity to actual job needs? Email tied the sale to Gooseberry Project needs, so obligation limited to the amount actually used (~6,825 tons). Email set a definite quantity ("will need 12,000 tons") and did not condition purchase on actual later needs. Court: Not a requirements contract; 12,000 tons was the agreed quantity.
Is the appeal moot because Buyer paid the judgment? Payment was made to abate interest while expressly reserving appeal rights. Acceptance of payment and satisfaction of judgment waives appeal; appeal is moot. Court: Under Utah Resources exception, Buyer preserved appeal by clearly reserving rights on the record; appeal not moot.

Key Cases Cited

  • Flowell Elec. Ass’n v. Rhodes Pump, LLC, 361 P.3d 91 (Utah 2015) (standard for reviewing summary judgment)
  • Utah Res. Int’l, Inc. v. Mark Techs. Corp., 342 P.3d 761 (Utah 2014) (preserving appellate rights despite paying judgment when reservation is clear on the record)
  • Salt Lake City Corp. v. Big Ditch Irrigation Co., 258 P.3d 539 (Utah 2011) (definition and treatment of requirements contracts under UCC)
  • Herm Hughes & Sons, Inc. v. Quintek, 834 P.2d 582 (Utah Ct. App. 1992) (UCC sections on contract formation and 2-207 analysis)
  • Bank of Am. v. Adamson, 391 P.3d 196 (Utah 2017) (appellate-briefing burden to cite authority and explain applicability)
  • Miller v. West Valley City, 397 P.3d 761 (Utah Ct. App. 2017) (appellant must show error in the basis for the lower court’s decision)
Read the full case

Case Details

Case Name: Scott Anderson Trucking v. Nielson Construction
Court Name: Court of Appeals of Utah
Date Published: Mar 19, 2020
Citations: 462 P.3d 822; 2020 UT App 43; 20180274-CA
Docket Number: 20180274-CA
Court Abbreviation: Utah Ct. App.
Log In