History
  • No items yet
midpage
435 S.W.3d 705
Mo. Ct. App.
2014
Read the full case

Background

  • Scheck Industrial (plaintiff) appeals amended judgment after bench trial favoring Tarlton (defendant) on plaintiff's account stated and breach-of-contract claims and on defendant's counterclaims for breach, warranty, indemnification, and attorney fees.
  • Subcontracted work involved welding eight drain-access collars into a penstock at Ameren Taum Sauk project; lower penstock steel was T-1, upper was A201, creating welding compatibility issues.
  • Subcontract incorporated contract documents, warranty, and a pay-if-paid clause; Plaintiff was to investigate conditions and independently determine welding criteria; indemnity clause (Part II(H)(I-17)) was included.
  • After initial welding, cracks appeared; it was learned the lower penstock was T-1 steel; attempts to repair with new welding methods failed; Briem Engineering recommended a different welding procedure.
  • Ameren ultimately paid for most work except $553,133.51; plaintiff sought this amount; trial court found plaintiff failed to perform work in a workmanlike manner and awarded defendant damages and attorney fees.
  • On appeal, the Missouri court affirmed, addressing challenges including the trial court's exclusion of plaintiff's retained expert and various contract-based defenses and counterclaims.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the trial court abused its discretion striking the retained expert Johnson was timely disclosed five weeks before trial and non-prejudicial Johnson was untimely disclosed, causing prejudice No abuse of discretion; untimely disclosure justified exclusion
Whether the amended judgment on account stated is against the weight of the evidence Defendant admitted owing for work and did not dispute invoices No express agreement or unconditional promise to pay; invoices unpaid due to Ameren claim Not against the weight of the evidence; no account stated established
Whether plaintiff breached the contract and waived rights by accepting defective work Work was performed in a good and workmanlike manner and/or Defendant waived defects by acceptance Evidence shows non-workmanlike performance and no waiver; contract documents required independent verification Substantial evidence supports breach; no waiver; contract documents interpretation favorable to defendant
Whether the pay-if-paid clause is applicable or moot Pay-if-paid clause is ambiguous and should not create a condition precedent Claus e is applicable as a condition precedent to payment Moot because plaintiff failed to perform work in a workmanlike manner; pay-if-paid not invoked
Whether defendant's counterclaims for breach of contract, breach of warranty, mitigation, indemnification, and attorney fees were proper Warrants claims did not apply; defendant failed to mitigate damages Substantial evidence supports breach, warranty applicability, proper mitigation, and indemnification; fees pleaded properly All counterclaims and fee awards upheld; no reversible error

Key Cases Cited

  • Legg v. Certain Underwriters at Lloyd’s of London, 18 S.W.3d 379 (Mo. App. W.D. 1999) (untimely expert disclosure justifies exclusion; broad discretion governs)
  • Wilkerson v. Prelutsky, 943 S.W.2d 643 (Mo. Banc 1997) (untimely expert disclosure constitutes abuse of discovery; prejudice indicated)
  • Houston v. Crider, 317 S.W.3d 178 (Mo. App. S.D. 2010) (against-weight-of-the-evidence standard requires firm belief judgment is wrong)
  • Chisler v. Staats, 502 S.W.2d 424 (Mo. App. 1973) (invoices alone do not prove account stated unless explicit acknowledgment)
  • R.K. Matthews Inv., Inc. v. Beulah Mae Housing, LLC, 379 S.W.3d 890 (Mo. App. W.D. 2012) (workmanlike performance standard in construction contracts)
  • Grant Selsor & Sons Lumber Co. v. Wood, 872 S.W.2d 150 (Mo. App. S.D. 1992) (account stated elements: prior dealings, agreement on amount, acknowledgment or promise)
  • Burns & McDonnell Engineering Co. v. Torson Constr. Co., 834 S.W.2d 755 (Mo. App. W.D. 1992) (indemnity contracts; indemnity against loss vs. liability)
  • Williams Constr., Inc. v. Weher Constr. LLC, 403 S.W.3d 660 (Mo. App. S.D. 2012) (first-to-breach rule in contract performance)
  • Business Men’s Assurance Co. of Am. v. Graham, 891 S.W.2d 438 (Mo. App. W.D. 1994) (mitigation of damages; damages must be proven with reasonable certainty)
  • Kracman v. Ozark Electric Coop., Inc., 816 S.W.2d 688 (Mo. App. S.D. 1991) (measure of damages for breach of indemnity agreement against loss)
Read the full case

Case Details

Case Name: Scheck Industrial Corporation v. Tarlton Corporation, Defendant/Respondent.
Court Name: Missouri Court of Appeals
Date Published: Jul 15, 2014
Citations: 435 S.W.3d 705; 2014 Mo. App. LEXIS 767; 2014 WL 3428402; ED100371
Docket Number: ED100371
Court Abbreviation: Mo. Ct. App.
Log In
    Scheck Industrial Corporation v. Tarlton Corporation, Defendant/Respondent., 435 S.W.3d 705