History
  • No items yet
midpage
764 S.E.2d 913
S.C.
2014
Read the full case

Background

  • SCE&G obtained an initial BLRA base load review order in 2009 approving construction of two nuclear units at V.C. Summer and setting capital cost and schedule parameters.
  • In May 2012 SCE&G petitioned the Public Service Commission to modify the original order to increase capital costs by about $283 million and to delay Unit 2 completion (overall project completion advanced by 7.5 months but Unit 2 delayed 11 months).
  • Sierra Club, SCEUC (industrial customers), and a residential intervenor participated; a hearing was held in October 2012.
  • The Commission approved $278.05 million of the requested increases and the schedule update, finding changes reflected normal evolution and not imprudence. Rehearing was denied.
  • Appellants appealed, arguing the Commission applied the wrong BLRA provision (§58-33-270 rather than §58-33-275), that the Commission should have reexamined prudence of continuing construction at the update stage, and that evidence did not show the costs were prudent.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
1. Which BLRA provision governs a petition to modify an existing base load review order? Appellants: §58-33-275(E) should apply because the additional costs could have been anticipated and thus are deviations subject to the deviation/deprudence standard. SCE&G/ORS: §58-33-270(E) governs modifications to an existing BLRA order; §58-33-275 applies only after a proven deviation. Court: Affirmed Commission — §58-33-270(E) controls modification proceedings; §58-33-275(E) applies to post-deviation recovery challenges.
2. Must the Commission re-evaluate the prudence of continuing construction in a modification proceeding? Appellants: Commission should reassess overall project prudence at the update stage (reopen initial prudency review). SCE&G/ORS: BLRA forecloses repeated relitigation; initial comprehensive prudency review is binding unless deviation/abandonment standards are met. Court: No. Reopening initial prudency on each update would defeat BLRA’s purpose; Commission not required to reassess overall prudence at modification stage.
3. Did the record support the Commission’s finding that the additional costs and schedule changes were not the result of imprudence? Appellants: SCEUC/Sierra Club contend SCE&G failed to prove prudence of the cost increases and schedule changes. SCE&G/ORS: The Commission’s findings are supported by substantial, technical evidence from the hearing. Court: Substantial evidence supports the Commission’s factual findings; appellants failed to show the decision was unsupported.
4. Can parties use the modification proceeding to convert the proceeding into a deviation challenge requiring proof by preponderance? Appellants: Yes — conversion warranted because costs could have been anticipated. SCE&G/ORS: No — such conversion is improper; statutory scheme separates modification and deviation processes. Court: No. The Commission correctly treated this as a modification under §58-33-270(E), not a deviation under §58-33-275(E).

Key Cases Cited

  • S.C. Energy Users Comm. v. Pub. Serv. Comm'n of S.C., 388 S.C. 486 (2010) (describing BLRA purpose and precluding recovery of imprudent contingency costs in initial review)
  • Friends of the Earth v. Pub. Serv. Comm'n of S.C., 387 S.C. 360 (2010) (interpreting §58-33-270(E) as permitting post-order modification petitions)
  • Duke Power Co. v. Pub. Serv. Comm'n of S.C., 343 S.C. 554 (2001) (establishing deferential standard of review for PSC decisions)
  • Hodges v. Rainey, 341 S.C. 79 (2000) (statutory construction: courts must give clear statutes their plain meaning)
Read the full case

Case Details

Case Name: SC Energy Users Committee v. SCE&G
Court Name: Supreme Court of South Carolina
Date Published: Oct 22, 2014
Citations: 764 S.E.2d 913; 410 S.C. 348; 27456
Docket Number: 27456
Court Abbreviation: S.C.
Log In