History
  • No items yet
midpage
SAM RODGERS PROPERTIES, INC. v. Chmura
61 So. 3d 432
| Fla. Dist. Ct. App. | 2011
Read the full case

Background

  • SRP, a home builder, contracted with Chmura to construct a Monterey on lot 31 in Pelican Pointe; base price disputes arose between $246,700 and $256,700.
  • A February 28, 2004 contract stated $246,700; a May 29, 2004 contract allegedly increased to $256,700, with the increase not signed by Chmura on the altered page.
  • SRP began construction in January 2006; Chmura did not make two draw payments; construction halted March 10, 2006.
  • SRP recorded a lien for $169,926 (April 26, 2006) and later an amended lien for $180,139 (August 30, 2006) reflecting additional work and costs.
  • SRP obtained a final foreclosure judgment, which this court previously vacated and remanded for a new trial; the current appeal follows remand.
  • Trial court found no meeting of the minds and deemed the altered contract unenforceable, ruling the contract and lien issues against SRP.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Was there a binding contract to build for $256,700? SRP Chmura There was a binding initial contract for $246,700; the later $10,000 increase lacked consent and is not enforceable.
If the $256,700 contract is unenforceable, can SRP recover under the initial contract? SRP Chmura SRP has a right to damages for breach of the initial valid contract; remand for damages on breach of contract and lien foreclosure.
Is the amended claim of lien fraudulent or valid, and how should foreclosure be determined? SRP Chmura Amended lien was not fraudulent; non-lienable items excised; original lien valid; remand to foreclose for amended amount less taxes/insurance.

Key Cases Cited

  • Rollins, Inc. v. Butland, 951 So.2d 860 (Fla. 2d DCA 2006) (elements of contract breach: existence, breach, damages)
  • Knowles v. C.I.T. Corp., 346 So.2d 1042 (Fla. 1st DCA 1977) (meeting of the minds essential to contract)
  • Leopold v. Kimball Hill Homes Fla., Inc., 842 So.2d 133 (Fla. 2d DCA 2003) (clear terms and mutual assent required for enforceable contract)
  • Delta Fire Sprinklers, Inc. v. OneBeacon Ins. Co., 937 So.2d 695 (Fla. 5th DCA 2006) (work within contract extends lien filing period)
  • Sharrard v. Ligon, 892 So.2d 1092 (Fla. 2d DCA 2004) (willful exaggeration required for fraudulent lien finding)
  • Politano v. GPA Const. Grp., 9 So.3d 15 (Fla. 3d DCA 2008) (excising nonlienable items without invalidating remaining lien)
  • Stevens v. Site Developers, Inc., 584 So.2d 1064 (Fla. 5th DCA 1991) (allowing lien in reduced amount without finding fraud)
  • McCown v. Pierce Construction, Inc., 552 So.2d 940 (Fla. 4th DCA 1989) (untimely amended lien; original lien enforceable if no prejudice)
  • Johnson Bailey Architects, P.C. v. Se. Brake Corp., 517 So.2d 776 (Fla. 2d DCA 1988) (enforcing original lien when amended lien untimely)
  • Swedroe, Robert M. Architect/Planners, A.I.A., P.A., 565 So.2d 349 (Fla. 1st DCA 1990) (test for final furnishing of lien work; contract scope matters)
  • Michnal v. Palm Coast Dev., Inc., 842 So.2d 927 (Fla. 4th DCA 2003) (flexible evaluation of contract scope; no hard rules)
  • Rollins, Inc. v. Butland, 951 So.2d 860 (Fla. 2d DCA 2006) (considerations for breach damages)
Read the full case

Case Details

Case Name: SAM RODGERS PROPERTIES, INC. v. Chmura
Court Name: District Court of Appeal of Florida
Date Published: Apr 27, 2011
Citation: 61 So. 3d 432
Docket Number: 2D10-1260
Court Abbreviation: Fla. Dist. Ct. App.