History
  • No items yet
midpage
Rockies Express Pipeline LLC v. Interior
730 F.3d 1330
Fed. Cir.
2013
Read the full case

Background

  • Rockies Express (pipeline developer) and Interior (MMS/DOI) executed a Precedent Agreement requiring Interior to reserve 2.5% of pipeline capacity and to execute firm transportation service agreements (FTSAs), with ten-year reservation payments, as part of a RIK (royalty-in-kind) program.
  • The Precedent Agreement included an Appendix B FTSA form and limited Interior’s right to terminate except if directed by legislative action or a change in federal policy; Rockies Express refused a termination-for-convenience clause during negotiation.
  • Interior executed the West FTSA and shipped gas, but refused to execute the East FTSA in 2008 citing an Office of Solicitor memo and demanding FAR provisions; negotiations failed and Interior stopped shipping and refused to sign the East FTSA.
  • Rockies Express terminated the Precedent Agreement (claiming material breach) and submitted claims; DOI later announced a phase-out of the RIK program (December 2009 memorandum) but said existing RIK contracts would be honored.
  • The CBCA found Interior breached and awarded reservation charges through October 31, 2009, reasoning the Secretary’s policy decision would have led Interior to terminate FTSAs; Rockies Express appealed that limitation on damages, and Interior cross-appealed jurisdiction and liability.

Issues

Issue Rockies Express’ Argument Interior’s Argument Held
Whether the Precedent Agreement is a procurement contract under the Contract Disputes Act It is a binding procurement contract obligating Interior to execute FTSAs and pay reservation charges It is an agreement to agree, not a procurement contract (no services acquired, no expenditure yet) Precedent Agreement is a procurement contract under the CDA; CBCA had jurisdiction (affirmed)
Whether Interior materially breached by refusing to execute the Rockies Express East FTSA Refusal to sign East FTSA and failure to pay post-April 1, 2009 reservation charges breached the agreement FTSA would have been illegal or required FAR/termination-for-convenience clause; contracting officer lacked authority Interior materially breached; defenses (illegality, Christian clause, lack of authority) rejected (affirmed breach)
Whether Interior’s later policy announcement limited Rockies Express’s damages Post-breach policy change would not excuse liability; Rockies Express is entitled to damages through contract term Secretary’s phase-out constituted a change in federal policy that would have allowed termination under Provision 3(b), limiting damages to Oct 31, 2009 Secretary’s announcement did not effect a policy change that vitiated the FTSA (existing contracts to be honored); Board erred to limit damages (reversed)
Proper measure and timing of damages after material breach Rockies Express seeks full contract balance (profit and costs) through term; termination upon breach entitles it to damages to end of term Damages limited by post-breach policy action and mitigation/offsets Rockies Express entitled to pecuniary loss of anticipated and unearned profits through contract term; Board must calculate damages on remand (affirm liability, reverse damage limitation)

Key Cases Cited

  • G.L. Christian & Associates v. United States, 312 F.2d 418 (Ct. Cl. 1963) (court may read required contract clauses into government contracts)
  • Cities Service Helex, Inc. v. United States, 543 F.2d 1306 (Ct. Cl. 1976) (material breach permits injured party to terminate and recover damages to end of contract)
  • Northern Helex Co. v. United States, 524 F.2d 707 (Ct. Cl. 1975) (post-breach termination by government ineffective to limit damages)
  • John Reiner & Co. v. United States, 325 F.2d 438 (Ct. Cl. 1963) (when illegality is not obvious, contractor receives benefit of reasonable doubts)
  • Maxima Corp. v. United States, 847 F.2d 1549 (Fed. Cir. 1988) (contractor entitled to remedy when government cannot claim illegality to escape liability)
Read the full case

Case Details

Case Name: Rockies Express Pipeline LLC v. Interior
Court Name: Court of Appeals for the Federal Circuit
Date Published: Sep 13, 2013
Citation: 730 F.3d 1330
Docket Number: 2012-1055, 2012-1174
Court Abbreviation: Fed. Cir.