Robey v. Parnell
33,852
| N.M. Ct. App. | Jan 10, 2017Background
- Robey (Plaintiff) hired Parnell (Defendant) to design and drill a replacement irrigation well after his old well failed; parties proceeded on a written estimate plus oral promises (no formal contract).
- The estimate described a 120-foot well with an annular seal and an expected useful life of about fifty years; final invoice showed 115 feet and a concrete pad but no annular seal, and Plaintiff was told the difference was immaterial.
- The well was completed in September 2007; by March 2011 it produced only sediment and air and effectively failed.
- Plaintiff sued for breach of contract, negligent and knowing misrepresentation, consequential damages, and statutory claims under New Mexico’s Unfair Trade Practices Act (UPA). After a bench trial the district court found an express warranty (50-year durability), breach, failure to meet workmanlike standards, awarded contract remedies (total paid) plus consequential damages, but dismissed UPA/unconscionability claims.
- On appeal the Court of Appeals affirmed liability findings (express warranty, breach, failure to meet workmanlike standard), affirmed most damages, reversed one $2,500 element of consequential damages as speculative, and rejected both parties’ other challenges (including UPA and unconscionability claims).
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Defendant made an express warranty that the well would last ~50 years | Robey: Parnell expressly promised ~50‑year life and that became part of the bargain | Parnell: No express warranty; customary practice doesn't include such warranties and statute of frauds requires writing | Court: Affirmed express warranty — verbal promise became part of the basis of the bargain and was supported by substantial evidence |
| Whether Defendant breached the contract by not building to estimate/specifications | Robey: Contract based on estimate and oral promises; deviations (depth, missing annular seal) breached contract | Parnell: Estimate not a binding prescription; not bound to exact estimate specs | Court: Breach affirmed — parties contracted based on the estimate and evidence supported material deviations and failure to perform |
| Whether Defendant failed to design/construct the well in a workmanlike manner (implied warranty) | Robey: Expert testimony showed design/construction defects and regulatory departures caused failure | Parnell: Well functioned for ~4 years; failures are speculative and owner maintenance caused problems | Court: Affirmed — substantial evidence (expert testimony, deviations from standards) supported the workmanlike‑performance breach |
| Whether consequential damages were properly awarded and supported | Robey: Consequential items (filing fees, clean‑out, evaluations, plugging cost) flowed from breach | Parnell: Some items (notably $2,500 plugging estimate) speculative; consequential damages require foreseeability/special circumstances | Court: Mostly affirmed consequential damages as foreseeable and supported by receipts/exhibits, but reversed $2,500 plugging estimate as speculative; rejected need for special‑circumstances showing in these facts |
| Whether negligent misrepresentation supported damages | Robey: District court relied in part on negligent misrepresentation | Parnell: District court found key elements of negligent misrepresentation lacking — cannot support damages | Court: Although negligent misrep. claim failed on elements, its inclusion as alternative basis was harmless (no prejudice) because contract breach independently supported the damages |
| Whether UPA/unconscionable trade practice claims should have succeeded | Robey: Misrepresentations and poor value (well lasted <4 years vs promised 50) make UPA/unconscionability succeed | Parnell: Plaintiff failed to show knowingly made misrepresentations or gross disparity in value | Court: Affirmed dismissal — Plaintiff failed to prove the UPA’s higher "knowingly made" element and provided no objective evidence of gross disparity in value |
Key Cases Cited
- Davis v. Merrick, 66 N.M. 226, 345 P.2d 1042 (N.M. 1959) (no implied warranty that a drilled well will produce; distinguishes implied vs express warranties)
- Salazar v. D.W.B.H., Inc., 144 N.M. 828, 192 P.3d 1205 (N.M. 2008) (express warranty need not be in writing; must be part of basis of the bargain)
- Sunnyland Farms, Inc. v. Central N.M. Elec. Coop., Inc., 301 P.3d 387 (N.M. 2013) (consequential damages foreseeability and when special circumstances may be required)
- First Nat’l Bank in Albuquerque v. Sanchez, 112 N.M. 317, 815 P.2d 613 (N.M. 1991) (party bearing burden must present accurate evidence of damages; speculative estimates disallowed)
- State ex rel. King v. B & B Inv. Grp., Inc., 329 P.3d 658 (N.M. 2014) (UPA unconscionability inquiry focuses on objective gross disparity between price paid and value received)
- Gooch v. Coleman, 22 N.M. 45, 159 P. 945 (N.M. 1916) (custom cannot contradict plain terms of an express contract)
- Cotter v. Novak, 57 N.M. 639, 261 P.2d 827 (N.M. 1953) (negligence vs knowing standard discussion in premises liability context)
- Baker v. Benedict, 92 N.M. 283, 587 P.2d 430 (N.M. 1978) (appellate court will not disturb findings when evidence substantially supports them)
