History
  • No items yet
midpage
Road & Highway Builders, LLC v. Northern Nevada Rebar, Inc.
128 Nev. 384
| Nev. | 2012
Read the full case

Background

  • Builders contracted with NDOT for a 2.3-mile freeway project requiring substantial rebar and RCBs; NNR bid based on NDOT plans.
  • Builders contemplated using precast RCBs and began change approvals without informing NNR, while still using NNR’s bid for the project.
  • A Subcontract was executed reserving Builders’ right to order changes and establishing a fixed unit price with final quantities to match NDOT unless written otherwise.
  • Builders sought precast RCBs from another supplier; NDOT approved substitutions for about 80% of poured-in-place RCBs after Subcontract execution.
  • Disputes over changes led NNR to seek equitable adjustment and payment; Builders ceased payments and terminated NNR, causing delays and increased costs.
  • Jury found for NNR on counterclaims, awarding $700,000 in compensatory damages and $300,000 in punitive damages; district court denied post-trial motions.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Fraud in inducement if contract terms contradict NNR contends Builders induced reliance by promising full rebar under contract terms. Builders argues fraud cannot lie where contract terms permit changes and quantities. Fraud claim fails as a matter of law; contract terms control.
Proper basis for compensatory damages NNR seeks damages for labor, materials, and lost profits under breach of contract and implied covenant. Damages limited to actual costs given at-will termination; profits not recoverable. Compensatory damages affirmed; recoveries for costs and lost profits supported by contract/implied covenant.
Punitive damages when fraud claim fails Punitive damages justified by fraud and breach independent of contract. Punitive damages improper where claim sounds in contract and no tort basis. Punitive damages reversed; no basis to award punitive damages.

Key Cases Cited

  • Tallman v. First Nat. Bank, 66 Nev. 248, 208 P.2d 302 (Nev. 1949) (fraud cannot arise from promises contrary to written terms)
  • Brinderson-Newberg v. Pacific Erectors, 971 F.2d 272 (9th Cir. 1992) (integrated contract bars parol promises conflicting with terms)
  • Sherrodd, Inc. v. Morrison-Knudsen Co., 815 P.2d 1135 (Mont. 1991) (fraud exception to parol rule when not directly contradicting contract terms)
  • Hilton Hotels v. Butch Lewis Productions, 109 Nev. 1043, 862 P.2d 1207 (Nev. 1993) (contractual covenant of good faith and fair dealing informs damages/tort distinction)
  • Amoroso Const. v. Lazovich and Lazovich, 107 Nev. 294, 810 P.2d 775 (Nev. 1991) (punitive damages not available for pure contract breaches)
  • Dalton Properties, Inc. v. Jones, 100 Nev. 422, 683 P.2d 30 (Nev. 1984) (at-will termination and lost profits analysis for unearned profits)
Read the full case

Case Details

Case Name: Road & Highway Builders, LLC v. Northern Nevada Rebar, Inc.
Court Name: Nevada Supreme Court
Date Published: Aug 9, 2012
Citation: 128 Nev. 384
Docket Number: No. 55542; No. 56499
Court Abbreviation: Nev.