History
  • No items yet
midpage
279 F.Supp.3d 846
D. Minnesota
2017
Read the full case

Background

  • The Fargo‑Moorhead Flood Risk Project (Project) is a cross‑border flood control plan developed by the U.S. Army Corps of Engineers (Corps) and a non‑Federal sponsor, the Fargo‑Moorhead Flood Diversion Board of Authority (Diversion Authority); Corps issued feasibility/NEPA documents and Congress authorized the Project in WRRDA‑2014.
  • The Diversion Authority applied to Minnesota DNR for a Dam Safety and Public Waters Work Permit; DNR denied the Permit in October 2016, finding the Project did not adequately protect Minnesota public interests and violated state environmental/floodplain requirements.
  • Despite the denial, the Corps and Diversion Authority executed a Project Partnership Agreement (PPA) allocating Federal and Non‑Federal work and indicating split delivery of construction responsibilities; parties began project activities on the North Dakota side.
  • Richland/Wilkin Joint Powers Authority (JPA) and Minnesota DNR sued, alleging among other claims that the Corps and Diversion Authority violated WRRDA‑2014, 33 U.S.C. § 2232, MERA, Minnesota water statutes, and NEPA; they sought preliminary injunctions to halt construction until Minnesota permits issued.
  • The Corps moved to dismiss on sovereign immunity, lack of final agency action, prudential standing, statutory inapplicability, and NEPA grounds; Diversion Authority moved to dismiss JPA’s WRRDA claim for lack of private right of action. The Court granted preliminary injunctive relief and resolved several motions to dismiss.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the PPA is a "final agency action" for APA review PPA is a binding agreement that consummates agency decisionmaking and creates rights/obligations Corps: PPA is implementation step; final action were ROD/Chief’s Report Held: PPA is a final agency action under Bennett; APA review available
Whether sovereign immunity bars APA claims against Corps DNR/JPA rely on APA review of PPA; sovereign immunity waived for final agency actions Corps: no final agency action identified, so immunity bars suit Held: APA waiver applies because PPA is final action; dismissal denied as to WRRDA/§2232 claims (some NEPA claim dismissed)
Whether 33 U.S.C. § 2232 applies to split‑delivery projects and requires state permits before non‑Federal work begins DNR/JPA: §2232 covers "water resources development projects" including split delivery; non‑Federal sponsor must obtain any required state/federal permits before carrying out project; Corps must monitor Corps: §2232 limited to independent non‑Federal conduct or does not apply here Held: §2232 unambiguously applies to projects as defined and requires permits; Corps’ monitoring duty exists; plaintiffs likely to succeed on §2232 claim
Whether WRRDA §7002 precludes application of state permitting or otherwise preempts state law DNR/JPA: §7002 conditions and Chief’s Report require compliance with state laws; Corps signing PPA before permits was arbitrary/capricious Corps/Diversion Auth: congressional authorization and "substantially in accordance with" language allow flexibility; federal law preempts state permitting Held: §7002 requires compliance with conditions in Chief’s Report, including state law; WRRDA does not preempt Minnesota permitting; plaintiffs have a fair chance of success
Whether NEPA requires a supplemental EIS given DNR permit denial JPA: new circumstances (permit denial) trigger SEIS duty Corps: Corps already considered DNR concerns in FEIS/FFREIS; no new significant information requiring SEIS Held: JPA failed to plausibly allege SEIS necessity; NEPA claim dismissed against Corps
Whether WRRDA/§2232 creates a private right of action enforceable against Diversion Authority JPA: WRRDA contemplates state compliance and benefits state/local entities; implies enforceable rights Diversion Auth: No express private right; statutes do not imply cause of action against non‑Federal sponsor Held: WRRDA does not create an implied private right of action against Diversion Authority; that count dismissed against Diversion Authority

Key Cases Cited

  • FDIC v. Meyer, 510 U.S. 471 (immunity of the United States unless waived)
  • Bennett v. Spear, 520 U.S. 154 (two‑part test for final agency action under APA)
  • Hawkes Co. v. U.S. Army Corps of Engineers, 782 F.3d 994 (reviewability of Corps jurisdictional determinations; discussion of finality issues)
  • Louisiana State v. U.S. Army Corps of Engineers, 834 F.3d 574 (contract/agreement can constitute final agency action)
  • Marsh v. Oregon Natural Resources Council, 490 U.S. 360 (standard for when an agency must prepare a supplemental EIS)
  • Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402 (scope of arbitrary and capricious review under APA)
Read the full case

Case Details

Case Name: Richland/Wilkin Joint Powers Authority v. United States Army Corps of Engineers
Court Name: District Court, D. Minnesota
Date Published: Sep 7, 2017
Citations: 279 F.Supp.3d 846; 0:13-cv-02262
Docket Number: 0:13-cv-02262
Court Abbreviation: D. Minnesota
Log In
    Richland/Wilkin Joint Powers Authority v. United States Army Corps of Engineers, 279 F.Supp.3d 846