History
  • No items yet
midpage
505 B.R. 388
Bankr. D.P.R.
2014
Read the full case

Background

  • Remand from the First Circuit required recalculation of Eichleay-based extended overhead damages using the percentage-of-direct-costs method where applicable and a determination of whether pre-judgment interest is appropriate, including its rate and accrual periods.
  • The District Court remanded to the Bankruptcy Court for proceedings consistent with the First Circuit’s mandate.
  • Redondo originally sought pre-judgment interest and extended overhead damages against PRHTA for three projects under Puerto Rico law.
  • The First Circuit vacated Eichleay-based overhead damages and directed recalculation, and returned the pre-judgment interest issue to determine rate and periods.
  • On remand, the parties filed stipulations; Redondo urged 6% pre-judgment interest under Article 1061 and extended overhead under Eichleay, while PRHTA argued waiver and a different approach/rate under Puerto Rico law.
  • The court ultimately held Redondo is entitled to 6% pre-judgment interest from substantial completion dates, and ordered further stipulations on how to compute extended overhead damages (percent-of-direct-costs vs Eichleay) per the First Circuit mandate.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Pre-judgment interest under Article 1061 Redondo seeks 6% pre-judgment interest from substantial completion dates PRHTA argues no pre-judgment interest or a different basis/rate Yes; 6% pre-judgment interest from substantial completion dates
Method for extended overhead damages Extent damages should be calculated using percentage-of-direct-costs for extra work Eichleay should apply where delays are not due to extra work Remand for calculation; either percentage-of-direct-costs (where applicable) or Eichleay for stand-by periods, per evidence
Standby requirement for Eichleay formula Standby applicable to partial/total suspensions Delay must be due to a stand-by condition; project never fully suspended Standby can be met via partial stoppages; need evidence of delay patterns
Scope of stipulations on extra work Extra work was “necessary but unanticipated” or compensated Record unclear; need stipulations to classify delays Remand to file stipulations briefs addressing whether extra work was necessary and unanticipated and the applicable method

Key Cases Cited

  • In re Redondo Construction Corp. v. Puerto Rico Highway and Transportation Authority (In re Redondo), 678 F.3d 115 (1st Cir. 2012) (vacated Eichleay damages and remanded for recalculation; pre-judgment interest to be determined)
  • P.J. Dick Inc. v. Principi, 324 F.3d 1364 (Fed. Cir. 2003) (three-prong test for Eichleay applicability; burden-shifting framework)
  • Republic Sec. Corp. v. Puerto Rico Aqueduct and Sewer Authority, 674 F.2d 952 (1st Cir. 1982) ( Puerto Rico civil-law interest matters; basis for Article 1061 recognizable in federal courts)
Read the full case

Case Details

Case Name: Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In re Redondo Construction Corp.)
Court Name: United States Bankruptcy Court, D. Puerto Rico
Date Published: Jan 13, 2014
Citations: 505 B.R. 388; Bankruptcy No. 02-02887(ESL); Adversary Nos. 03-00192(ESL), 03-00194(ESL), 03-00195(ESL)
Docket Number: Bankruptcy No. 02-02887(ESL); Adversary Nos. 03-00192(ESL), 03-00194(ESL), 03-00195(ESL)
Court Abbreviation: Bankr. D.P.R.
Log In
    Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In re Redondo Construction Corp.), 505 B.R. 388