Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.)
678 F.3d 115
1st Cir.2012Background
- Three contracts between Redondo and the Puerto Rico Highways and Transportation Authority for Patillas, Dorado-Toa Alta, and Mayagüez projects; unanticipated site conditions and flawed design caused delays and cost overruns; debtor completed all projects and sought additional compensation including subcontractor costs; bankruptcy filings and adversary proceedings led to a $12,028,311.92 award plus prejudgment interest; authority challenged rulings on notice, extended overhead, subcontractor standing, and prejudgment interest; district court affirmed, and First Circuit reviewed de novo with some forfeiture determinations.
- The bankruptcy court found Authority responsible for delays and site-condition-driven costs; it held Mayagüez notice satisfied by substantial actual notice despite lack of written notice; it awarded extended overhead using Eichleay broadly but did not separate compensated vs. uncompensated delays; it awarded prejudgment interest; the court remanded for recalculation of overhead and for prejudgment interest determinations; issues of standing and preservation were raised and evaluated on appeal.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Authority forfeited its challenges on appeal | Redondo argues claims forfeited | Authority contends not all issues were preserved | Only one claim forfeited; others preserved or timely raised under Rule 59(e) |
| Whether Mayagüez project damages were barred for lack of written notice | Redondo asserts substantial compliance with notice suffices | Authority argues strict Blue Book written-notice requirement | Substantial compliance/actual notice suffices; no waiver of subcontractor claims |
| Whether extended overhead damages were correctly awarded | Redondo contends Eichleay should apply to all delays; alternative methods for direct costs applicable | Authority argues Eichleay appropriate for all delays | Vacate Eichleay-based portions; remand for calculation using direct-cost percentage where applicable and Eichleay only for stoppages/delays as described |
| Whether prejudgment interest was properly awarded | Redondo seeks prejudgment interest under 41 U.S.C. § 7109(a)(1) or Puerto Rico Rule 44.3(b) | Authority argues no federal contract party; Puerto Rico choice law applies | Remand to district court to determine if prejudgment interest is appropriate and rate/duration; no clear entitlement |
| Whether debtor had standing to assert subcontractor claims | Redondo asserts entitlement to include subcontractor damages | Authority argues lack of standing under Severin doctrine | Severin-based challenge forfeited; standing issue treated as forfeited/not preserved |
Key Cases Cited
- United Elec., Radio & Mach. Workers of Am. v. 163 Pleasant St. Corp., 960 F.2d 1080 (1st Cir. 1992) (preservation/forfeiture principles in appeals)
- DiMarco-Zappa v. Cabanillas, 238 F.3d 25 (1st Cir. 2001) (affirmative defenses and sua sponte error rules)
- Crowe v. Bolduc, 365 F.3d 86 (1st Cir. 2004) (Rule 59(e) standards; prejudgment interest considerations)
- Boston Gas Co. v. Century Indem. Co., 529 F.3d 8 (1st Cir. 2008) (prejudgment interest under Rule 59(e) and related procedures)
- Crowe v. Bolduc, 365 F.3d 86 (1st Cir. 2004) (prejudgment interest and preservation)
- P.J. Dick Inc. v. Principi, 324 F.3d 1364 (Fed. Cir. 2003) (Eichleay damages scope in federal contracts)
- Freeman v. Package Mach. Co., 865 F.2d 1331 (1st Cir. 1988) (state-law prejudgment interest principles in federal cases)
