862 S.E.2d 259
S.C.2021Background
- Ray purchased a 1920s house in 1985 built over a preexisting 24-inch terra cotta pipe (the Pipe) that runs under and behind her property at the low point of a 29-acre watershed.
- Three City-owned stormwater pipes collect runoff and discharge into a catch basin on College Avenue that connects to the Pipe; that system has routed water through the Pipe for roughly a century.
- Ray observed settlement and sinkhole events over the years and learned in 2008 from City employees that the Pipe ran from College Avenue toward her porch; she later sued the City on November 6, 2012 alleging inverse condemnation and trespass.
- During a contemporaneous City sewer project the City severed all three stormwater pipes feeding the catch basin, stopping flow through the Pipe; after Ray filed suit and her counsel demanded the City not reconnect, the City reconnected the pipes and flow resumed.
- The circuit court granted summary judgment to the City on inverse condemnation (dismissing that claim); the court of appeals reversed, finding a triable issue whether the reconnection was an affirmative, positive, aggressive act; the Supreme Court affirmed as modified and remanded.
- The Court held Ray’s recovery is limited by the three-year statute of limitations: pre‑2012 damage is time‑barred (Ray learned of the problem in 2008), so only damage attributable to the City’s November 2012 reconnection remains at issue.
Issues
| Issue | Ray's Argument | City’s Argument | Held |
|---|---|---|---|
| Whether reconnecting the stormwater pipes after suit was an "affirmative, positive, aggressive act" sufficient for inverse condemnation | Reconnection was an affirmative, directed act that restarted harmful water flow and thus is a taking | Reconnection was maintenance or merely a refusal to follow Ray’s demand — a failure to act, not an affirmative act | Reconnection can be an affirmative act; Court found a genuine issue of material fact and reversed summary judgment on that basis |
| Whether Ray presented evidence that the reconnection caused new or additional damage (causation/quantum) | Structural engineer’s supplemental report predicted increased flow and risk of additional structural damage after reconnection | No evidence the November 2012 reconnection caused distinct, additional damage | Engineer’s report raises a triable issue of fact; remand for determination on actual damages caused by reconnection |
| Effect of statute of limitations on recovery | Claim limited to damages from the 2012 reconnection, so timely | Plaintiff discovered the problem by 2008; claims for earlier damage are time‑barred | Damages occurring more than three years before the 2012 filing are barred; Ray may recover only for damage caused by the November 2012 reconnection |
| Does absence of evidence that City installed the Pipe preclude liability | City has nonetheless been directing stormwater into the Pipe for decades, creating responsibility for reconnection act | City argues it did not install the Pipe and original taking (if any) occurred long ago | Installation origin is irrelevant to the reconnection question; liability turns on City’s act of directing water into the Pipe and resulting damage |
Key Cases Cited
- Hawkins v. City of Greenville, 358 S.C. 280, 594 S.E.2d 557 (Ct. App. 2004) (analyzes affirmative‑act requirement for inverse condemnation)
- WRB Ltd. P’ship v. Cty. of Lexington, 369 S.C. 30, 630 S.E.2d 479 (2006) (plaintiff must prove a government’s affirmative, aggressive, positive act caused damage)
- Marietta Garage, Inc. v. S.C. Dep’t of Pub. Safety, 352 S.C. 95, 572 S.E.2d 306 (Ct. App. 2002) (elements of inverse condemnation)
- Gray v. S.C. Dep’t of Highways & Pub. Transp., 311 S.C. 144, 427 S.E.2d 899 (Ct. App. 1992) (inverse condemnation elements; permanence/public‑use considerations)
- Lanham v. Blue Cross & Blue Shield of S.C., Inc., 349 S.C. 356, 563 S.E.2d 331 (2002) (standard of review for summary judgment)
- Dean v. Ruscon Corp., 321 S.C. 360, 468 S.E.2d 645 (1996) (discovery rule for statute of limitations)
