History
  • No items yet
midpage
Ray Bell Construction Company, Inc. v. State of Tennessee, Tennessee Department of Transportation
2011 Tenn. LEXIS 1143
Tenn.
2011
Read the full case

Background

  • Ray Bell Construction contracted with TDOT on May 28, 2003 to reconstruct the I-240/I-40 interchange, with completion originally due by December 15, 2006.
  • The contract included an incentive of $10,000 per day (up to $2,500,000 total) for completing all work by December 15, 2006 and a disincentive for days beyond that date.
  • Extension provisions allow time extensions for delays caused by conditions beyond the contractor’s control, governed by the Standard Specifications; an Order of Precedence clause gives Special Provisions control over Standard Specifications.
  • TDOT proposed Supplemental Agreement 24 extending the completion and disincentive dates by 137 days but keeping the incentive date at December 15, 2006; Ray Bell refused.
  • Engineer's post-completion determination found the contract substantially complete on December 17, 2006; TDOT later offered a 137-day extension for completion and disincentive but not the incentive date.
  • Claims Commission awarded Ray Bell the maximum incentive and other relief based on latent ambiguity; Court of Appeals affirmed; the Tennessee Supreme Court reversed, holding the contract unambiguous and not permitting an incentive-date extension.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Is the incentive date extension authorized by the contract? Ray Bell argued ambiguity requiring extrinsic evidence to permit extension of the incentive date. TDOT argued the contract unambiguously limits the incentive date to December 15, 2006. Incentive date extension is not permitted; contract unambiguous.
Does the Extension Provision permit extending the incentive date when time is extended for conditions beyond the contractor's control? Ray Bell contends extensions may extend all relevant dates, including the incentive date. TDOT contends Extension Provision extends only completion and disincentive dates. Extension Provision extends completion and disincentive dates, not the incentive date.
What is the effect of the contract's order-of-precedence on the dispute? Ray Bell relies on ambiguity to justify extrinsic evidence and broader interpretations. TDOT relies on the plain, controlling language of the Special Provision over Standard Specifications. Special Provision (Completion) governs over Standard Specifications (Extension); contract is unambiguous.

Key Cases Cited

  • Maggart v. Almany Realtors, Inc., 259 S.W.3d 700 (Tenn. 2008) (courts interpret contracts to avoid rendering provisions meaningless)
  • Allstate Ins. Co. v. Watson, 195 S.W.3d 609 (Tenn. 2006) (initial task is to determine ambiguity in contract language)
  • Planters Gin Co. v. Fed. Compress & Warehouse Co., 78 S.W.3d 885 (Tenn. 2002) (determine whether contract language is ambiguous)
  • Whitehaven Cmty. Baptist Church v. Holloway, 973 S.W.2d 592 (Tenn. 1998) (contract interpretation within four corners if unambiguous)
Read the full case

Case Details

Case Name: Ray Bell Construction Company, Inc. v. State of Tennessee, Tennessee Department of Transportation
Court Name: Tennessee Supreme Court
Date Published: Dec 12, 2011
Citation: 2011 Tenn. LEXIS 1143
Docket Number: E2009-01803-SC-R11-CV
Court Abbreviation: Tenn.