History
  • No items yet
midpage
163 N.E.3d 323
Ind. Ct. App.
2020
Read the full case

Background:

  • Ranger (seller) and Caccavale (buyer) signed a Purchase Agreement for ~13 acres; sections J ("Flood Area/Other") and K ("Inspections") were central to the dispute.
  • Buyer obtained a pre-closing soil inspection reporting wetlands and that Starke County would refuse a septic permit; buyer refused to close and tendered a mutual release which Ranger refused.
  • Ranger sued for breach and sought specific performance; Judge Pera granted summary judgment on liability for Ranger (denying rescission) but reserved remedy/damages and did not enter final written judgment on liability.
  • At a later damages hearing before a different judge (Webber), testimony about wetlands/septic and permit denial was presented; Judge Webber reversed Pera’s partial summary judgment, entered judgment for Caccavale, and relied in part on that hearing testimony.
  • Appellant moved to correct error arguing due process and that the court improperly relied on evidence not designated in the summary-judgment phase; the Court of Appeals held no due process violation but reversed and remanded because the trial court abused its discretion by considering testimony introduced after the summary-judgment designation deadline.

Issues:

Issue Plaintiff's Argument Defendant's Argument Held
Whether the trial court abused its discretion by reconsidering and reversing partial summary judgment based on evidence presented at the damages hearing Ranger: Reconsideration violated due process and relied on "ambush" testimony presented after summary-judgment designations Caccavale: Trial court may revisit interlocutory rulings under Trial Rules; summary-judgment on liability was not final so reconsideration permitted Court: No due process violation, but reversal was an abuse of discretion when based on testimony not designated in summary-judgment proceedings; reversed and remanded (citing Mitchell)
Proper construction of Sec. J (flood-only vs. separate location-based use limitations) Ranger: Sec. J is a flood-plain provision only; rescission requires flood-plain condition Caccavale: Sec. J also provides a separate contingency for any location-based building/use limitations materially interfering with intended use Court: Majority declined to decide the merits on appeal and remanded; concurrence would hold Sec. J contains two separate contingencies and favor buyer on that legal point
Effect of Sec. K inspection waiver on buyer’s rescission claim based on inability to obtain septic permit Ranger: K’s waiver bars buyer’s claim as a waived "condition of the Property" and Ranger could have cured Caccavale: K applies to inspections of existing improvements, not location-based permit limitations Court: Majority did not resolve; concurrence would treat septic-permit denial as a location-based use limitation not barred by the inspection waiver
Whether summary-judgment evidentiary materials were properly limited by Trial Rule 56 when court reconsidered earlier ruling Ranger: Only materials designated before the original summary judgment could be considered Caccavale: Trial court has discretion to reconsider interlocutory orders Court: Trial court must consider only Rule 56 materials that were before it at the time the original order was entered when revisiting summary judgment; consideration of later hearing testimony was improper

Key Cases Cited

  • Mitchell v. 10th and The Bypass, LLC, 3 N.E.3d 967 (Ind. 2014) (when reconsidering summary judgment, court may consider only Rule 56 materials that were before it when the original order was entered)
  • Santelli v. Rahmatullah, 993 N.E.2d 167 (Ind. 2013) (abuse-of-discretion review of motion to correct error)
  • Celadon Trucking Servs., Inc. v. United Equip. Leasing, LLC, 10 N.E.3d 91 (Ind. Ct. App. 2014) (standard for reviewing reconsideration of trial-court rulings)
  • Bruno v. Wells Fargo Bank, N.A., 850 N.E.2d 940 (Ind. Ct. App. 2006) (due process requires notice and opportunity to be heard)
  • Care Grp. Heart Hosp., LLC v. Sawyer, 93 N.E.3d 745 (Ind. 2018) (contract interpretation is a question of law reviewed de novo)
  • Alexander v. Linkmeyer Dev. II, LLC, 119 N.E.3d 603 (Ind. Ct. App. 2019) (summary-judgment review standard mirrors trial court's application)
Read the full case

Case Details

Case Name: Ranger Team Building, LLC v. Vince Caccavale (mem. dec.)
Court Name: Indiana Court of Appeals
Date Published: Dec 28, 2020
Citations: 163 N.E.3d 323; 20A-PL-547
Docket Number: 20A-PL-547
Court Abbreviation: Ind. Ct. App.
Log In