History
  • No items yet
midpage
899 F.3d 511
8th Cir.
2018
Read the full case

Background

  • U.S. Army Corps of Engineers awarded general contract for Grand Prairie Pump Station to Kinder in June 2010; Kinder subcontracted MSEW work to Manning for $950,000.
  • The project suffered extensive, excusable delays (weather, scheduling, prerequisite work by Kinder and third parties); Manning was repeatedly prevented from starting on schedule.
  • Kinder repeatedly threatened Manning with delay-related damages and demanded strict tolerances; Kinder told COE a much later completion date while pressuring Manning to finish sooner.
  • Manning mobilized in August 2011, changed panel suppliers after COE rejected the first supplier’s panels, completed ~27.5 of 40 vertical feet, and was directed by Kinder to suspend work in March 2012; another contractor finished the wall and COE accepted work containing defects similar to those Kinder had criticized.
  • Kinder sued Manning for breach; Manning counterclaimed for wrongful termination and unpaid labor/materials. After a five-day bench trial the district court found Kinder committed the first material breach, wrongfully terminated Manning, and awarded Manning $215,578.24 for work performed prior to termination.

Issues

Issue Plaintiff's Argument (Kinder) Defendant's Argument (Manning) Held
Which party committed the first material breach? Manning first materially breached by failing to pay suppliers and lacking stamped shop drawings. Kinder’s threats, interference with Manning’s supplier (EarthTec), and failure to give assurances were the first material breaches. Court: Kinder committed the first material breach; Manning’s failures were not material.
Whether Kinder’s termination of Manning was wrongful Kinder contends Manning should have continued performance and sought government remedies; FAR obligations require continuing performance. Manning continued performing until Kinder directed suspension; termination by Kinder was a breach. Court: Termination was wrongful breach by Kinder; Manning was not required to continue after termination.
Whether Manning’s alleged defects were material Kinder contends Manning’s panels violated specs and justified termination. Manning argued alleged defects were not material; industry tolerances were tighter than customary and COE’s interpretation was unreasonable. Court: Alleged defects were not material; Manning substantially performed.
Whether damages awarded were supported by the record Kinder argues evidence insufficient to support the $215,578.24 award. Manning testified to labor/materials expended (27.5 of 40 ft completed), supporting the claimed costs. Court: Award supported; damages for labor/materials before wrongful termination were not speculative.

Key Cases Cited

  • PHL Variable Ins. Co. v. 2008 Christa Joseph Irrevocable Tr., 782 F.3d 976 (8th Cir.) (standard of review for bench trial: legal conclusions de novo, factual findings for clear error)
  • Bennie v. Munn, 822 F.3d 392 (8th Cir.) (describing clear-error standard and deference to trial court credibility findings)
  • Matt Miller Co. v. Taylor-Martin Holdings, LLC, 393 S.W.3d 68 (Mo. Ct. App.) (materiality of breach is a question of fact)
  • Barnett v. Davis, 335 S.W.3d 110 (Mo. Ct. App.) (Missouri’s “first to breach” rule)
  • R.J.S. Sec., Inc. v. Command Sec. Servs., Inc., 101 S.W.3d 1 (Mo. Ct. App.) (only a material breach excuses other party’s performance; Restatement §241 factors)
  • Guidry v. Charter Commc’ns, Inc., 269 S.W.3d 520 (Mo. Ct. App.) (continuing to accept benefits can waive right to assert prior breach)
  • High Life Sales Co. v. Brown-Forman Corp., 823 S.W.2d 493 (Mo.) (damages are question of fact)
  • Overcast v. Billings Mut. Ins. Co., 11 S.W.3d 62 (Mo.) (measure of contract damages: place injured party in position contract performed)
  • Best Buy Builders, Inc. v. Siegel, 409 S.W.3d 562 (Mo. Ct. App.) (certainty required for damages amount)
  • Harvey v. Timber Res., Inc., 37 S.W.3d 814 (Mo. Ct. App.) (when fact of damage is clear, less certainty required as to amount)
Read the full case

Case Details

Case Name: Randy Kinder Excavating, Inc. v. JA Manning Constr. Co.
Court Name: Court of Appeals for the Eighth Circuit
Date Published: Aug 7, 2018
Citations: 899 F.3d 511; 17-2886
Docket Number: 17-2886
Court Abbreviation: 8th Cir.
Log In
    Randy Kinder Excavating, Inc. v. JA Manning Constr. Co., 899 F.3d 511