History
  • No items yet
midpage
939 F.3d 1029
9th Cir.
2019
Read the full case

Background

  • Tule Wind proposed a 128-turbine wind development split into Phase I (65 turbines on federal land; BLM jurisdiction) and Phase II (20 turbines on Ewiiaapaayp tribal ridgeline; BIA jurisdiction).
  • BLM prepared a single EIS covering both phases and identified unavoidable adverse impacts to golden eagles, particularly from Phase II.
  • Tule prepared a Supplemental Project‑Specific Avian and Bat Protection Plan for Phase II; FWS and others criticized its methods and conclusions.
  • BIA issued a Record of Decision (ROD) approving Phase II, relying on the EIS and the Supplemental Protection Plan and requiring Tule to apply for an eagle-take permit under the Bald and Golden Eagle Protection Act (BGEPA) before operation.
  • Plaintiffs challenged BIA’s approval under NEPA and the APA and argued BIA should have required a BGEPA permit pre‑construction; the district court granted judgment for defendants.
  • The Ninth Circuit affirmed, rejecting Plaintiffs’ challenges to BIA’s NEPA/APA analysis and its decision not to condition approval on pre‑construction issuance of a BGEPA permit.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
1. Reliance on BLM EIS / failure to explain not adopting mitigation MM BIO‑10f and apparent discrepancy on eagle impacts BIA improperly relied on BLM EIS and failed to explain why it did not implement MM BIO‑10f or reconcile the EIS’s finding of unavoidable eagle impacts with the ROD’s conclusion BIA in fact followed MM BIO‑10f by evaluating each turbine, used the Supplemental Protection Plan to establish final risk criteria, consulted with FWS, and thus had no unexplained departure Court: BIA complied with MM BIO‑10f and the ROD’s analysis was consistent with the EIS plus mitigation; no legal error.
2. Alternatives analysis (partial ridgeline build) EIS unlawfully omitted a reasonable mid‑range alternative authorizing some but not all Phase II turbines Plaintiffs preserved the issue; but BIA/BLM argued the EIS considered reasonable alternatives for the overall project (including a 63‑turbine mid‑range alternative) and the project must be viewed as a whole Court: Issue preserved; because Phase I and II are one connected project the EIS’s mid‑range alternative for the whole project was sufficient under NEPA.
3. Need for Supplemental EIS (SEIS) based on new info in the Supplemental Plan and comments New surveys and FWS comments supplied significant new information requiring an SEIS Defendants: the new information merely confirmed risks already disclosed in the EIS; BIA took a "hard look" in the ROD and Supplemental Plan Court: New information was not significant in the Marsh sense; BIA maintained a hard look; no SEIS required.
4. Conditioning approval on BGEPA permit pre‑construction / legality of approval BIA should have required Tule to obtain a BGEPA permit prior to construction; approval otherwise facilitates unlawful take Defendants: BIA required Tule to apply and comply with BGEPA; enforcement and permitting are FWS/Tule responsibilities; prior precedent forecloses invalidating agency action that authorizes lawful development absent sanctioning unlawful take Court: BIA’s approach was lawful and not arbitrary; it reasonably declined to condition approval on prior issuance of a permit.

Key Cases Cited

  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary and capricious standard for agency action)
  • Marsh v. Oregon Natural Resources Council, 490 U.S. 360 (1989) (when supplemental EIS required; significance standard)
  • Protect Our Communities Found. v. Jewell, 825 F.3d 571 (9th Cir. 2016) (prior decision addressing BLM’s approval and limits on agency responsibility for third‑party illegal takes)
  • Muckleshoot Indian Tribe v. United States Forest Service, 177 F.3d 800 (9th Cir. 1999) (insufficient alternatives where only no‑action and similar alternatives considered)
  • Friends of the Clearwater v. Dombeck, 222 F.3d 552 (9th Cir. 2000) (agencies must remain alert to new information and take a hard look)
  • Klamath‑Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 387 F.3d 989 (9th Cir. 2004) (programmatic analysis cannot substitute for required site‑specific analysis)
  • Western Watersheds Project v. Abbey, 719 F.3d 1035 (9th Cir. 2013) (distinguishing programmatic and site‑specific adequacy of alternatives and analysis)
  • Anderson v. Evans, 371 F.3d 475 (9th Cir. 2004) (agency action invalid where it sanctions unlawful third‑party conduct)
Read the full case

Case Details

Case Name: Protect Our Communities v. Darryl Lacounte
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Sep 23, 2019
Citations: 939 F.3d 1029; 17-55647
Docket Number: 17-55647
Court Abbreviation: 9th Cir.
Log In