240 F. Supp. 3d 1055
S.D. Cal.2017Background
- Tule Wind Project: two phases — Phase I (65 turbines on BLM land) and Phase II (20 turbines on tribal trust land); BLM prepared a 2011 Final EIS with BIA as a cooperating agency.
- The 2011 EIS analyzed alternatives and stated that final siting/acceptance of Phase II turbines would be at the discretion of the appropriate land-management agency in consultation with resource agencies (e.g., FWS, CDFG).
- After the EIS, BIA collected additional eagle telemetry data, revised an Avian and Bat Protection Plan (ABPP), received memoranda from FWS and CDFG expressing that Phase II was "high-risk" for golden eagles and recommending modifications, but did not adopt all recommendations.
- BIA issued a December 2013 Record of Decision (ROD) approving Phase II with mitigation measures (curtailment periods, requirement to seek an eagle-take permit, monitoring) and concluded impacts would not be significant after mitigation.
- Plaintiffs sued under NEPA and the APA, alleging (1) improper reliance on the 2011 EIS, (2) failure to prepare a supplemental EIS based on post-2011 information and project changes, and (3) withholding of material from the public. Court previously dismissed plaintiffs’ Eagle Act and MBTA claims.
- The Court held that BIA permissibly relied on the 2011 EIS, that the EIS adequately considered golden-eagle impacts and alternatives, and that no new information or changes triggered the NEPA supplementation requirement; therefore defendants’ summary judgment motions were granted and plaintiffs’ motion denied.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether BIA could rely on the 2011 EIS as a cooperating agency when approving Phase II | BIA could not rely exclusively because it failed to follow EIS language limiting authorization where turbines exceeded "acceptable risk" and because the EIS didn’t meaningfully analyze Phase II alternatives | The EIS expressly left final risk criteria and authorization to the appropriate land manager (BIA here); the EIS analyzed a reasonable range of alternatives and was intended to serve cooperating agencies | Court: BIA permissibly relied on the 2011 EIS; EIS did not bind BIA to accept FWS/CDFG risk determinations and alternatives analysis was adequate |
| Whether BIA had a duty to prepare a supplemental EIS based on post-2011 agency memoranda and telemetry data | FWS memoranda, CDFG comments, and new telemetry data constituted significant new information requiring supplementation | The post-2011 materials largely confirmed concerns already considered in the 2011 EIS and therefore were not "significant" under NEPA’s supplementation standard | Court: No supplemental EIS required because new information was not a materially different picture warranting another "hard look" |
| Whether BIA had to supplement the EIS because the ROD authorized up to 20 turbines on trust land while the EIS referenced 18 turbines | The numerical difference was a substantial change relevant to environmental concerns that required supplementation | BIA explained EIS had analyzed siting of two turbines straddling BLM and trust land; final engineering could place them on trust land — impacts were within the EIS’s analyzed scope | Court: Not a substantial change; within spectrum of alternatives analyzed; supplementation not required |
| Whether BIA violated NEPA’s public disclosure requirements by withholding germane materials | Plaintiffs argued BIA withheld highly germane materials bearing on impacts and alternatives | Defendants showed BIA participated in EIS process, circulated the draft, addressed comments, and made additional documents available for comment (ABPP, Fire Plan) | Court: Public-disclosure requirements satisfied; additional materials did not trigger supplement or disclosure violations |
Key Cases Cited
- Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment burden allocation)
- Anderson v. Liberty Lobby, 477 U.S. 242 (summary judgment standard and inferences)
- Motor Vehicle Mfrs. Ass'n v. State Farm, 463 U.S. 29 (arbitrary-and-capricious standard under APA)
- Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519 (NEPA exhaustion/agency process)
- Dep’t of Transp. v. Public Citizen, 541 U.S. 752 (NEPA exhaustion/issue preservation)
- Marsh v. Ore. Nat. Res. Council, 490 U.S. 360 (NEPA supplementation — significance requirement)
- Norton v. S. Utah Wilderness All., 542 U.S. 55 (limits on judicially compelled agency action under APA)
- City of Sausalito v. O’Neill, 386 F.3d 1186 (9th Cir.) (administrative-arbitrary-and-capricious review)
- Protect Our Communities Found. v. Jewell, 825 F.3d 571 (9th Cir.) (prior appellate decision addressing Tule EIS and related NEPA issues)
- State of Cal. v. Block, 690 F.2d 753 (9th Cir.) (rule-of-reason standard for alternatives in NEPA)
