History
  • No items yet
midpage
916 F.3d 1006
Fed. Cir.
2019
Read the full case

Background

  • VA issued a Solicitation for Offers (SFO) for leased space in Parma, Ohio for a VA outpatient clinic; SFO §4.2.7 required compliance with Interagency Security Committee (ISC) security criteria and included a Physical Security Table listing seven labeled spaces.
  • Amendment #1 (issued pre-award) clarified the security level question, stating: “Based upon ISC Standards, the project would be a Level II.” Premier acknowledged receipt of Amendment #1 before signing the Lease, which incorporated the SFO and amendments.
  • After award, VA communications were inconsistent about whether ISC standards or the VA Life‑Safety Guide controlled; VA ultimately instructed Premier that the ISC Level II requirement applied to the entire building and that Premier must comply at no additional cost.
  • Premier attempted to obtain ISC documents (initially denied to non‑federal entities); VA later provided ISC materials. Premier contended ISC Level II applied only to the seven listed spaces and sought payment for costs of applying Level II to the whole facility.
  • Premier filed a certified claim and then suit in the Court of Federal Claims seeking compensation for alleged extra costs; the Court of Federal Claims granted summary judgment to the government, holding Amendment #1 unambiguously required ISC Level II for the entire project.
  • On appeal, the Federal Circuit affirmed, concluding Amendment #1’s reference to the “project” unambiguously means the whole facility and thus Premier’s Level II design/construction was within the contract scope.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Lease requires ISC Level II for the entire facility Amendment #1 is ambiguous and applies only to the seven spaces listed in the Physical Security Table Amendment #1 unambiguously requires ISC Level II for the entire project/facility; it was incorporated into the Lease Held for defendant: Amendment #1 unambiguously requires ISC Level II for the whole facility
Whether Amendment #1 resolved any ambiguity in §4.2.7 Amendment #1 should be read narrowly to clarify only those tabled spaces Amendment #1 was issued to clarify §4.2.7 and its use of “project” reasonably refers to the entire facility Held: Amendment #1 resolves ambiguity and its plain meaning of “project” covers the entire Parma Clinic
Whether extrinsic evidence (post‑award VA communications) changes contract meaning VA’s inconsistent post‑award directions show ambiguity and estop VA from enforcing broader ISC requirement without payment Contract language (including Amendment #1) is clear; extrinsic inconsistent statements do not alter an unambiguous term Held: Post‑award communications do not override the clear contract language requiring ISC Level II
Whether Premier is entitled to extra costs for applying ISC Level II Premier sought compensation for additional design/construction costs incurred applying ISC Level II to whole building Government refused payment, asserting requirements were in SFO and Amendment #1 before bid/award Held: Premier not entitled—work was within contractual scope because Amendment #1 put Premier on notice pre‑award

Key Cases Cited

  • Hartman v. United States, 694 F.3d 96 (Fed. Cir.) (standard of review for mixed questions on appeal to Federal Circuit)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment standard)
  • Varilease Tech. Grp., Inc. v. United States, 289 F.3d 795 (Fed. Cir.) (contract interpretation is generally amenable to summary judgment)
  • NVT Techs., Inc. v. United States, 370 F.3d 1153 (Fed. Cir.) (contract must be read as a whole; ambiguity is a question of law)
  • McAbee Constr., Inc. v. United States, 97 F.3d 1431 (Fed. Cir.) (may not resort to extrinsic evidence when contract language is unambiguous)
  • C. Sanchez & Son, Inc. v. United States, 6 F.3d 1539 (Fed. Cir.) (definition of unambiguous contract term)
  • Metric Constructors, Inc. v. Nat’l Aeronautics & Space Admin., 169 F.3d 747 (Fed. Cir.) (both party interpretations must be reasonable to show ambiguity)
  • Coast Fed. Bank, FSB v. United States, 323 F.3d 1035 (Fed. Cir.) (when language is unambiguous, plain meaning controls)
Read the full case

Case Details

Case Name: Premier Office Complex of Parma, LLC v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Feb 19, 2019
Citations: 916 F.3d 1006; 2018-1231
Docket Number: 2018-1231
Court Abbreviation: Fed. Cir.
Log In