History
  • No items yet
midpage
Premier Office Complex of Parma, LLC v. United States
134 Fed. Cl. 83
| Fed. Cl. | 2017
Read the full case

Background

  • Premier Office Complex of Parma, LLC contracted with the VA under Lease No. V101-08-RP-0034 to build an outpatient clinic in Parma, Ohio; the lease incorporated the Solicitation for Offers (SFO) and Amendments 1–3.
  • SFO §4.2.7 (Physical Security Requirements) referenced physical security measures for listed "spaces or areas" and discussed ISC security levels for facilities; a Physical Security Table listed particular rooms with discrete requirements.
  • Amendment #1 (issued before award and initialed by Premier) stated: "Based upon the ISC Standards, the project would be a Level 2," which the VA later treated as requiring ISC Level II for the entire facility.
  • After construction began, VA staff inconsistently directed Premier about which security standards to apply (VA Design Guide vs. ISC Standards); VA ultimately required ISC Level II design for the whole project.
  • Premier built the facility to ISC Level II, then sought $964,356.40 for alleged out-of-scope costs, claiming the ISC requirement applied only to table-listed spaces; VA denied the claim and the Court of Federal Claims granted the government summary judgment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the VA required ISC Level II design for the entire building, creating an out-of-scope change Premier: §4.2.7 and the Physical Security Table limit ISC requirements to listed spaces; Amendment #1 merely corrected a sentence, not imposed project-wide ISC standards U.S.: Amendment #1 unambiguously applied ISC Level II to the whole "project," and §4.2.7 and Amendment #1 together put offerors on notice pre-award Court: Amendment #1 unambiguously required ISC Level II for the entire project; no compensable change by the VA
Whether ambiguity in §4.2.7 excused Premier from earlier inquiry Premier: §4.2.7 was ambiguous and latently so; no duty to seek clarification U.S.: Offerors were on notice (Amendment #1 clarified security level prior to bid) Court: §4.2.7 was latently ambiguous, but Amendment #1 resolved it; Premier still bound by Amendment #1
Whether ISC Standards were incorporated into the contract Premier: ISC Standards were not expressly incorporated and conflict with Premier's incorporated proposal U.S.: SFO language, Amendment #1, and incorporation clauses made ISC requirements binding Court: Amendment #1’s project-wide ISC Level II statement resolved any incorporation question in government’s favor
Whether VA communications (conflicting directions) created grounds for relief Premier: VA’s later conflicting directions demonstrate uncertainty and estop VA U.S.: Conflicting communications at most show initial ambiguity; final directive matched Amendment #1 Court: Inconsistent engineer communications evidenced ambiguity but do not overcome unambiguous Amendment #1; no relief granted

Key Cases Cited

  • Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment standard)
  • Anderson v. Liberty Lobby, 477 U.S. 242 (materiality and genuine dispute standard for summary judgment)
  • Varilease Tech. Group, Inc. v. United States, 289 F.3d 795 (contract interpretation is a question of law amenable to summary judgment)
  • McAbee Constr. v. United States, 97 F.3d 1431 (contract interpretation begins with plain language)
  • Granite Constr. Co. v. United States, 962 F.2d 998 (interpret contract as whole to give reasonable meaning to all parts)
  • Cmty. Heating & Plumbing v. Kelso, 987 F.2d 1575 (contractor’s interpretation of latent ambiguity adopted only if reasonable)
  • Triax Pac. v. West, 130 F.3d 1469 (ambiguities in government contracts normally resolved against the drafter)
Read the full case

Case Details

Case Name: Premier Office Complex of Parma, LLC v. United States
Court Name: United States Court of Federal Claims
Date Published: Sep 22, 2017
Citation: 134 Fed. Cl. 83
Docket Number: 14-1223C
Court Abbreviation: Fed. Cl.