History
  • No items yet
midpage
Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd.
159 N.E.3d 1201
Ohio Ct. App.
2020
Read the full case

Background

  • Premier Construction supplied building materials for Maple Glen’s 18‑unit apartment project after Maple Glen’s owner, Indira Murthy, signed Premier’s written estimate in September 2017.
  • The estimate listed descriptions, unit prices, and a $165,666.08 grand total; the Qty column was left blank but the Total/Each and Total columns matched.
  • Premier delivered first‑floor materials in October 2017, invoiced $24,331.20 (due on receipt), and later issued additional invoices (including $3,447 for retrieval) that went unpaid.
  • Because construction was postponed, Premier retrieved the delivered materials, sold some over the following year for about $18,000, and claimed roughly $7,000 remaining damages.
  • Premier recorded a mechanic’s lien in January 2018 for the unpaid balance and sued for breach of contract and lien foreclosure; the trial court dismissed both claims.
  • The court of appeals reversed, holding the estimate could be read to include an implicit quantity and that a mechanic’s lien may arise from an intent to use materials in improvement; the case was remanded to determine breach and damages.

Issues

Issue Plaintiff's Argument (Premier) Defendant's Argument (Maple Glen) Held
Whether the written estimate formed an enforceable UCC contract despite a blank quantity field The invoice totals equal the unit totals, implying a quantity of one for each line; parties manifested intent to contract and delivery occurred The estimate lacks an essential quantity term and is too vague (no quantity, delivery place/time, payment terms), so the statute of frauds bars enforcement Court: The quantity can be read as one from identical Total/Each and Total columns; UCC permits some open terms; reversed trial court and remanded to decide breach/damages
Whether Premier holds a valid mechanic’s lien where materials were delivered but later removed by Premier Lien is valid because materials were furnished and delivered with the intent they be used in the improvement (statute requires intent, not actual incorporation) Lien invalid because it depends on an invalid contract and because materials were not actually used on the improvement (they were removed) Court: Trial court erred; contract found enforceable and R.C. 1311.12(A)(1) requires intent to use, not proof of actual use; remanded to assess lien validity and enforcement

Key Cases Cited

  • McSweeney v. Jackson, 117 Ohio App.3d 623 (Ohio Ct. App. 1996) (standard of appellate review for contract existence is mixed law/fact).
  • Dyno Construction Co. v. McWane, 198 F.3d 567 (6th Cir. 1999) (price quotation may be an offer if sufficiently detailed and recipient’s assent completes the contract).
  • Robert V. Clapp Co. v. Fox, 124 Ohio St. 331 (Ohio 1931) (mechanic’s lien statutes construed strictly as to existence but liberally as to remedies).
  • Crock Constr. Co. v. Stanley Miller Constr. Co., 66 Ohio St.3d 588 (Ohio 1993) (reaffirming principles on construction of mechanics’ lien statutes).
Read the full case

Case Details

Case Name: Premier Const. Co., Inc. v. Maple Glen Apts. & Townhomes, Ltd.
Court Name: Ohio Court of Appeals
Date Published: Oct 5, 2020
Citation: 159 N.E.3d 1201
Docket Number: CA2020-03-011
Court Abbreviation: Ohio Ct. App.